Solar Permit in Omaha, Nebraska

Permit required

Yes, a permit is required

Before installing rooftop or ground-mounted solar panels or solar shingles; work can start only after the city building permit is approved.

Quick answer

Omaha requires a residential solar permit, applied for at OmahaPermits.com, for solar panels or solar shingles. The application needs a site plan showing fire code access pathways, an electrical diagram and spec sheets; the applicant must hold at least a Building Class E license and a master electrician must be attached before issuance. The building permit and the utility's net metering application (OPPD for most of Omaha) are submitted concurrently, the system gets building and electrical final inspections, and the utility witness-tests it before activation.

Issued by
City of Omaha Planning Department, Permits and Inspections Division
From an official source Verified

Who is pulling this permit?

Hire it out

Before you sign, ask the contractor:

  • Who pulls the permit, you or me, and is the permit fee included in the bid?
  • Which inspections will this job need, and who meets the inspector on site?

Nebraska's owner-builder rule (Neb. Rev. Stat. 81-2121(5); 48-2104(1)) sets what you may do on your own home without hiring anyone. Read the statute.

What a solar permit costs in Omaha

Fee basis
Project valuation
Fee schedule in force
Official scheduleRead .

Building permit fee by valuation, Omaha Municipal Code Sec. 43-91, Table 43-91 (for example $41.00 for the first $2,000.00 plus $9.53 for each additional $1,000.00 up to $25,000.00).

Solar thermal: 'Each solar collector array (including related piping and regulating devices)' $11.35 on the plumbing permit (Sec. 49-304).

Fees are the jurisdiction’s; we do not mark them up or estimate them.

How to apply in Omaha

General guide, not specific to this office

What a solar permit application usually includes, and which inspections usually follow, is much the same from place to place, so we explain it once: how a solar permit works, from application to final inspection. That guide describes common practice under the model codes. The office on this page sets the actual checklist.

City of Omaha Planning Department, Permits and Inspections Division

Solar Permit in Omaha compared with nearby Nebraska localities

LocalityPermit needed?ThresholdWhat each Nebraska schedule saysVerified
OmahaPermit requiredAny sizeBuilding permit fee by valuation, Omaha Municipal Code Sec. 43-91; the schedule has the rest
LincolnPermit requiredAny sizeElectrical Fees page: BASE FEE $30 plus per-item charges

Permitting activity in Omaha

In 2025, Omaha authorized permits for 3,776 new residential housing units (1,557 single-family, 2,219 in multi-family buildings), valued at $441M, down from 4,360 the year before. That works out to about 7.9 permits per 1,000 residents.

Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 478,393.

What else needs a permit in Omaha

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Bathroom Remodel PermitIt dependsWhen the remodel moves or adds plumbing, adds or alters wiring, or makes a structural...Plumbing: per-fixture and per-relocation fees with a $22.70 minimum (Sec. 49-304)
Deck PermitPermit requiredAny sizeValuation-based building permit fee, Omaha Municipal Code Sec. 43-91, Table 43-91: $1.00 to $2,000.00 total valuation, $41.00
Electrical PermitPermit requiredAny sizeOmaha Municipal Code Sec. 44-130: minimum fee on all electrical work $25.00
EV Charger PermitPermit requiredAny sizeSee schedule
Fence PermitPermit requiredAny sizeValuation-based building permit fee, Omaha Municipal Code Sec. 43-91, Table 43-91: $1.00 to $2,000.00 total valuation, $41.00
HVAC PermitPermit requiredAny sizeOmaha Municipal Code Sec. 40-109, Domestic-Residential: A/C units and heat pumps $50.00 first unit, $40.00 second
Patio PermitIt dependstotal area of new concrete or asphalt paving, outside the front yard setbackNot published
Plumbing PermitPermit requiredAny sizeOmaha Municipal Code Sec. 49-304: minimum permit fee $22.70
Pool PermitIt dependsBefore installing the pool's barrier fence, any pool accessory structure over 75 square...Plumbing permit line items, Omaha Municipal Code Sec. 49-304: each below ground swimming pool $58.90
Roof Replacement PermitIt dependsarea of roofing repaired or replaced (2 squares)Valuation-based building permit fee, Omaha Municipal Code Sec. 43-91, Table 43-91: $1.00 to $2,000.00 total valuation, $41.00
Shed PermitIt dependsfloor area of the accessory buildingValuation-based building permit fee, Omaha Municipal Code Sec. 43-91, Table 43-91: $1.00 to $2,000.00 total valuation, $41.00
Water Heater PermitPermit requiredAny sizeOmaha Municipal Code Sec. 49-304: minimum permit fee $22.70

Frequently asked questions

Do you need a solar permit in Omaha?
Yes, before installing rooftop or ground-mounted solar panels or solar shingles; work can start only after the city building permit is approved. If you are unsure how that applies to your project, call the City of Omaha Planning Department, Permits and Inspections Division at 402-444-5350 before you start.
How much does a solar permit cost in Omaha?
The fee wording from the official schedule is in the cost table on this page, as we read it on 16 Nov 2026. For the figure on your own project, call the City of Omaha Planning Department, Permits and Inspections Division at 402-444-5350.
Where do you apply for a solar permit in Omaha?
You can apply through the Omaha permit portal or contact the City of Omaha Planning Department, Permits and Inspections Division directly. The links are listed on this page.
Can a homeowner pull a solar permit themselves in Omaha?
Under Nebraska law (Neb. Rev. Stat. 81-2121(5); 48-2104(1)): Nebraska lets owners work on their own property. The State Electrical Act does not prohibit an owner from doing electrical work on a principal residence no larger than a single-family dwelling, or on farm property, and does not require that owner to be licensed (commercial, industrial, and public-use installations excluded). The Contractor Registration Act likewise says a person who works on, or has work performed on, his or her own property is not a contractor and need not register (48-2104). Whether the owner may pull the local building permit is decided by the county, city, or village; no state owner-builder disclosure form or resale restriction was found. Confirm how Omaha applies this before you apply.

From the Library

Solar Permit in other Nebraska localities

Everything above, sourced

How this solar permit page for Omaha was verified. 2 official sources: planning.omaha.gov, permits.cityofomaha.org; fee schedule: official document. Last checked by Mario Bailey, not confirmed with City of Omaha Planning Department, Permits and Inspections Division. Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Permit required
Check my project