EV Charger Permit in Wichita, Kansas
Permit required
Yes, a permit is required
An electrical permit is required to install an EV charger circuit.
Issued byMetropolitan Area Building and Construction Department (MABCD), joint City of Wichita and Sedgwick County
By Mario Bailey, verified against official sources
Quick answer
MABCD publishes nothing EV-specific, but the UBTC requires a MABCD permit for any electrical wiring for light, heat or power, and the only exemptions are temporary decorative lighting and communication wiring. A hardwired charger or new 240-volt circuit is therefore permitted electrical work.
Who is pulling this permit?
Apply yourself
Hire it out
Sponsored
A licensed electrician typically pulls the electrical permit as part of the install. If you have not picked one yet, compare a few quotes first.
Compare electrician quotes on Angi
Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.
When a permit is usually needed
An electrical permit is required to install an EV charger circuit.
What an EV charger permit costs in Wichita
How to apply in Wichita
In Wichita, in most of the US, installing a Level 2 (240 volt) home EV charger is handled as an electrical permit built around a load calculation and a single line diagram showing the new dedicated circuit. A Level 1 charger that simply plugs into an existing 120 volt outlet typically needs no permit unless new wiring is added.
What most EV charger permit applications include:
- For Wichita, a Level 2 charger needs its own dedicated 240 volt circuit and requires an electrical permit with inspection, since each outlet installed for EV charging must be fed by an individual branch circuit with no other outlets on it (NEC 625.40).
- For Wichita, the application includes an electrical load calculation showing the existing service panel has enough spare capacity for the added EVSE demand, worked out using the standard dwelling load calculation method (NEC 220.83).
- For Wichita, the breaker or other overcurrent device feeding the charger must be sized for continuous duty, rated at not less than 125 percent of the equipment's maximum load (NEC 625.41).
- Plan submittal typically includes a single line diagram showing conductor size, breaker size, conduit, and panel rating, plus the charger's manufacturer specifications, since the EVSE itself must be a listed product (NEC 625.5).
- For charging equipment rated over 60 amps or over 150 volts to ground, the application has to show a disconnecting means installed in a readily accessible location and capable of being locked open (NEC 625.43).
- For Wichita, the charger must be shown connected and fastened in place according to the manufacturer's installation instructions, whether it is hardwired or a plug in unit on a dedicated receptacle (NEC 625.44).
General submittal guidance from National Electrical Code (NFPA 70), Article 625 Electric Vehicle Charging System and Article 220 Load Calculations, 2017 to 2023 editions. Source. Metropolitan Area Building and Construction Department (MABCD), joint City of Wichita and Sedgwick County sets the exact checklist for Wichita.
Where to apply in Wichita:
Metropolitan Area Building and Construction Department (MABCD), joint City of Wichita and Sedgwick County
- 271 W. 3rd St. N., Suite 101, Wichita, KS 67202
- Phone: 316-660-1840
- Email: MABCD@sedgwick.gov
EV Charger Permit in Wichita compared with nearby Kansas localities
| Locality | Permit needed? | Threshold | What each Kansas schedule says | Verified |
|---|---|---|---|---|
| Wichita | Permit required | Any size | Electrical permit (UBTC Table I): Special Power Circuit $9.00 | |
| Overland Park | Permit required | Any size | See schedule |
Inspections and closing out your permit
In Wichita, a Level 2 EV charger installation gets a rough wiring inspection if any new conductors will be hidden inside walls, ceilings, or run underground, then a final inspection that checks the dedicated circuit, breaker sizing, any required GFCI protection, the disconnect, and the charger's listing before the permit closes.
- In Wichita: if new EVSE conductors will be concealed in a wall or ceiling, or run underground, they must pass a rough wiring inspection before being covered, since that inspection confirms the dedicated branch circuit required for the charger (NEC 625.40).
- In Wichita: at final inspection, the breaker or other overcurrent device serving the charger is checked to confirm it is properly rated for the continuous EV charging load (NEC 625.41).
- In Wichita: any receptacle installed for EV charging, as opposed to a hardwired connection, has to be checked for ground fault circuit interrupter protection (NEC 625.54).
- In Wichita: where the EVSE is rated over 60 amps or 150 volts to ground, the inspector confirms a lockable, readily accessible disconnecting means was installed (NEC 625.43).
- In Wichita: the inspector verifies the charger, along with its fittings and associated equipment, carries a nationally recognized testing laboratory listing (NEC 625.5).
- In Wichita: mounting height is checked against the manufacturer's instructions, with the coupling means generally required to sit at least 18 inches above an indoor floor or 24 inches above outdoor grade unless the equipment is listed otherwise (NEC 625.50).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Wichita permit portal or by phone at 316-660-1840.
Inspection sequence from National Electrical Code (NFPA 70), Article 625 Electric Vehicle Charging System, 2017 to 2023 editions. Source. An open permit left un-inspected can surface later in a title search or home sale.
Your EV Charger Permit checklist for Wichita
- Confirm the requirement. Yes, a permit is required. Usually needed: An electrical permit is required to install an EV charger circuit.
- Budget the fee. Electrical permit (UBTC Table I): Special Power Circuit $9.00; Permit Issuance Fee $25.00. The table has no EV-specific line; the special power circuit line is the likely fit but MABCD does not say so. Official fee schedule.
- Apply. In Wichita, in most of the US, installing a Level 2 (240 volt) home EV charger is handled as an electrical permit built around a load calculation and a single line diagram showing the new dedicated circuit. A Level 1 charger that simply plugs into an existing 120 volt outlet typically needs no permit unless new wiring is added. Start at the Wichita permit portal.
- Keep the office details handy. Metropolitan Area Building and Construction Department (MABCD), joint City of Wichita and Sedgwick County. Phone: 316-660-1840. Address: 271 W. 3rd St. N., Suite 101, Wichita, KS 67202.
- Plan for inspections. In Wichita, a Level 2 EV charger installation gets a rough wiring inspection if any new conductors will be hidden inside walls, ceilings, or run underground, then a final inspection that checks the dedicated circuit, breaker sizing, any required GFCI protection, the disconnect, and the charger's listing before the permit closes.
Compiled from the official sources on this page. Last checked .
Frequently asked questions
- Do you need an EV charger permit in Wichita?
- MABCD publishes nothing EV-specific, but the UBTC requires a MABCD permit for any electrical wiring for light, heat or power, and the only exemptions are temporary decorative lighting and communication wiring. A hardwired charger or new 240-volt circuit is therefore permitted electrical work. Always confirm with the Metropolitan Area Building and Construction Department (MABCD), joint City of Wichita and Sedgwick County before starting.
- How much does an EV charger permit cost in Wichita?
- Electrical permit (UBTC Table I): Special Power Circuit $9.00; Permit Issuance Fee $25.00. The table has no EV-specific line; the special power circuit line is the likely fit but MABCD does not say so. See the official fee schedule for current amounts.
- Where do you apply for an EV charger permit in Wichita?
- You can apply through the Wichita permit portal or contact the Metropolitan Area Building and Construction Department (MABCD), joint City of Wichita and Sedgwick County directly. The links are listed on this page.
- Can a homeowner pull an EV charger permit themselves in Wichita?
- Under Kansas law (K.S.A. 50-6,129(a)(1), 50-6,135(b)): Kansas has no statewide owner-builder statute because the state does not license general or residential contractors; whether a homeowner may pull permits is set by the local code. The one state contractor registration, for roofers, expressly exempts an owner who personally performs, or has employees perform, roofing work on the owner's own dwelling or other structures on residential or farm property the owner owns (K.S.A. 50-6,129(a)(1)). An owner acting as their own roofing contractor must still give the permit official the registration number of any registered roofing subcontractor working under the permit (K.S.A. 50-6,135(b)). Confirm how Wichita applies this before you apply.
From the Library
What else needs a permit in Wichita
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Bathroom Remodel Permit | It depends | A permit is needed when a bathroom remodel changes or adds anything (plumbing, wiring... | Not published |
| Deck Permit | It depends | deck with no overhead structure and not over any basement or story below | See schedule |
| Electrical Permit | Permit required | Any size | Electrical permit (UBTC Table I): 120 volt Circuit $2.00 each |
| Fence Permit | It depends | fences other than concrete or masonry; concrete or masonry fences are measured at 4 feet from the bottom of the footing to the top of the wall | Not published |
| HVAC Permit | Permit required | Any size | Mechanical permit (UBTC Table K): Forced Air Furnace (2,000 cfm or less) $14.00 |
| Plumbing Permit | Permit required | Any size | Plumbing permit (UBTC Table H): Waste Openings $4.50 each, plus a Permit Issuance Fee |
| Pool Permit | It depends | prefabricated pools with capacity of 5,000 gallons or less and walls entirely above ground | Not published |
| Roof Replacement Permit | It depends | roofing and/or siding repair or replacement within any 12-month period | Roofing permit: $0.05 per square foot (Min |
| Shed Permit | It depends | footprint of a non-fixed, movable storage cabinet with doors; any larger shed needs a location permit, and a building permit above 200 sq ft inside Wichita | Location permit: $50.00 (UBTC Table C) |
| Solar Permit | Permit required | Any size | ...includes a 'Photovoltaic System' line item plus a Permit Issuance Fee of... |
| Water Heater Permit | Permit required | Any size | Plumbing permit (UBTC Table H): Water Heater New or Replacement $9.00, plus a Permit... |
EV Charger Permit in other Kansas localities
Everything above, sourced
Code references
National and state model-code sections the general guidance on this page is drawn from. They are not Wichita documents; the office above sets the local rules.
How this EV charger permit page for Wichita was verified. 2 official sources: sedgwickcounty.org, sedgwickcounty.org; fee schedule: official document. Last checked by Mario Bailey, not confirmed with Metropolitan Area Building and Construction Department (MABCD), joint City of Wichita and Sedgwick County. Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page
Compare EV Charger Permit requirements across Kansas localities