Electrical Permit in New Castle County, Delaware
Permit required
Yes, a permit is required
Before electrical work: a licensed electrician has it inspected by a licensed inspection agency; an owner-occupant doing the work gets a State homeowner permit.
Quick answer
New Castle County does not permit or inspect electrical work. In unincorporated New Castle County, as everywhere in Delaware, electrical work by a State-licensed electrician is inspected by a Delaware-licensed electrical inspection agency, and an owner-occupant doing their own work obtains a homeowner electrical permit from the State (Board of Electrical Examiners, Division of Professional Regulation).
- Typical threshold
- Inspection by a State-licensed agency, or a State homeowner permit; New Castle County issues none
- Issued by
- New Castle County Department of Land Use
- Phone
- 302-395-5400
Who is pulling this permit?
Apply yourself
Hire it out
Sponsored
Electrical permits are usually pulled by the licensed electrician doing the job. If you are still choosing one, compare a few quotes first.
Compare electrician quotes on Angi
Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.
What an electrical permit costs in New Castle County
- Fee schedule in force
- Official scheduleRead .
- An electrical job needs no permit from New Castle County, which does not permit or inspect electrical work;
- its Schedule of Permit and Review Fees has no electrical permit line.
- A State-licensed electrician has the work inspected by a licensed Inspection Agency, and an owner-occupant may obtain an electrical permit from the State of Delaware;
- the County page publishes no fee for the inspection or the State permit.
Fees are the jurisdiction’s; we do not mark them up or estimate them.
How to apply in New Castle County
General guide, not specific to this office
What an electrical permit application usually includes, and which inspections usually follow, is much the same from place to place, so we explain it once: how an electrical permit works, from application to final inspection. That guide describes common practice under the model codes. The office on this page sets the actual checklist.
New Castle County Department of Land Use
- New Castle County Government Center, 87 Reads Way, New Castle, DE 19720
- Phone: 302-395-5400
- Email: permits@newcastlede.gov
Electrical Permit in New Castle County compared with nearby Delaware localities
| Locality | Permit needed? | Threshold | What each Delaware schedule says | Verified |
|---|---|---|---|---|
| New Castle County | Permit required | Inspection by a State-licensed agency, or a State homeowner permit; New Castle County issues none | An electrical job needs no permit from New Castle County, which does not permit or inspect electrical work | |
| Sussex County | Permit required | Any size | See schedule |
Your Electrical Permit checklist for New Castle County
- Confirm the requirement. Yes, a permit is required. Typical threshold: Inspection by a State-licensed agency, or a State homeowner permit; New Castle County issues none. Read the rule where we read it: newcastlede.gov: Figure Out What Permits You Need.
- Budget the fee. Price your project from the official fee schedule, which we read on .
- Apply. Start at the New Castle County permit portal.
- Keep the office details handy. New Castle County Department of Land Use. Phone: 302-395-5400. Email: permits@newcastlede.gov. Address: New Castle County Government Center, 87 Reads Way, New Castle, DE 19720.
Compiled from the official sources on this page. Last checked .
Permitting activity in New Castle County
In 2025, New Castle County authorized permits for 1,322 new residential housing units (1,128 single-family, 194 in multi-family buildings), valued at $169M, down from 1,586 the year before. That works out to about 2.2 permits per 1,000 residents.
Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 588,026.
What else needs a permit in New Castle County
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Bathroom Remodel Permit | It depends | Finish work (tiling, cabinets, counter tops) and in-place fixture reinstallation are exempt; new or moved plumbing, walls or circuits are not | See schedule |
| Deck Permit | It depends | Floor area of a free-standing deck no more than 30 inches above grade and not adjacent to or attached to the dwelling | See schedule |
| EV Charger Permit | Permit required | Electrical inspection by a State-licensed agency, or a State homeowner permit; New Castle County issues none | A home EV charger needs no permit from New Castle County, whose code exempts electric vehicle charging stations (Sec. 06.03.012.C) |
| Fence Permit | It depends | Only fences that serve as swimming pool barriers need a permit | Not published |
| HVAC Permit | Permit required | Any size | See schedule |
| Patio Permit | It depends | Height of a non-structural slab, patio or decorative hardscaping at any point | Not published |
| Plumbing Permit | Permit required | Any size | See schedule |
| Pool Permit | It depends | Pool, spa or hot tub wall height; any pool designed to connect to a circulation system needs a permit regardless of height | See schedule |
| Roof Replacement Permit | It depends | Share of the roof sheathing repaired or replaced during a re-roof | See schedule |
| Shed Permit | It depends | Floor area of a one-story detached accessory structure with an eave height of 10 feet or less and overall height of 20 feet or less; garages never qualify | See schedule |
| Solar Permit | It depends | Rooftop panels on a one- or two-family dwelling are exempt from the County building permit; electrical work still goes through the State | Not published |
| Water Heater Permit | Permit required | Any size | See schedule |
Frequently asked questions
- Do you need an electrical permit in New Castle County?
- Yes, before electrical work: a licensed electrician has it inspected by a licensed inspection agency; an owner-occupant doing the work gets a State homeowner permit. If you are unsure how that applies to your project, call the New Castle County Department of Land Use at 302-395-5400 before you start.
- How much does an electrical permit cost in New Castle County?
- The fee wording from the official schedule is in the cost table on this page, as we read it on 24 Nov 2026. For the figure on your own project, call the New Castle County Department of Land Use at 302-395-5400.
- Where do you apply for an electrical permit in New Castle County?
- You can apply through the New Castle County permit portal or contact the New Castle County Department of Land Use directly. The links are listed on this page.
- Can a homeowner pull an electrical permit themselves in New Castle County?
- Under Delaware law (9 Del. C. 6302(b); 9 Del. C. 4402(b); 24 Del. C. 1417; 24 Del. C. 1807(c)(2); 24 Del. C. 1820(c)(2); 16 Del. C. 7906(c)): Yes. Delaware homeowners may pull permits and do their own work, with trade-specific conditions. Sussex County's statute expressly lets any owner who wants to do their own work on their own building get a permit, and Kent County issues permits in the owner's name. For electrical work, a homeowner wiring their own home that is not for sale or rent must get a homeowner's permit from the Board of Electrical Examiners and pass a final inspection; swimming pools and hot tubs are excluded. Homeowners may do their own plumbing and HVACR work (but not gas piping) in their own home that is not for sale, rent or lease, and for plumbing must file a permit application with the inspection authority. Confirm how New Castle County applies this before you apply.
From the Library
Electrical Permit in other Delaware localities
Everything above, sourced
How this electrical permit page for New Castle County was verified. 1 official source: newcastlede.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with New Castle County Department of Land Use. Rules change; confirm before you build. How we verify.