Yes, a permit is required

Before replacing or installing a gas or electric water heater.

Confirmed on official page Verified

Issued byGreenville County Building Safety (Planning and Code Compliance)

By Mario Bailey, verified against official sources

Quick answer

Greenville County requires a permit to replace a water heater, gas or electric. Its Answer Book says mechanical permits are required for new equipment and change-outs, and the county prices water heaters on its mechanical fee schedule, at $36.00 for gas and $12.00 for electric. The statewide exemption list at S.C. Code 40-59-265 has no water heater item.

Who is pulling this permit?

Hire it out

Sponsored

Plumbers usually pull this permit as part of the replacement. If yours failed and you are choosing a plumber under time pressure, comparing a couple of quotes still pays.

Compare plumber quotes on Angi

Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.

When a permit is usually needed

Before replacing or installing a gas or electric water heater.

What a water heater permit costs in Greenville County

Line item
water heater permitBy formulaMechanical Permit Fees on the Residential Permit Fees schedule: Gas Water Heater $36.00 and Electric Water Heater $12.00, with a mechanical minimum fee per permit of $72.00. No effective date printed; the department's notice says residential permit fees rose 20 percent starting July 1, 2025.
Fee schedule in forceOfficial scheduleRead . Fees are the jurisdiction’s; we do not mark them up or estimate them.

How to apply in Greenville County

In Greenville County, replacing a residential water heater needs a permit before work starts, because swapping the appliance counts as installing regulated plumbing and fuel gas work, not an exempt repair. The application itself stays light: it identifies the work and its location, and most offices only ask for extra fuel or capacity details when the replacement changes fuel type or input size.

What most water heater permit applications include:

  • For Greenville County, a permit must be obtained before an owner or contractor installs, alters, or replaces any plumbing, fuel gas, or electrical system regulated by the code, which covers putting in a new water heater (IRC R105.1).
  • Water heater replacement is not on the code's short list of exempt plumbing work, and replacing defective piping with new material is expressly defined as new work that needs a permit and inspection (IRC R105.2).
  • For Greenville County, the application itself only has to identify and describe the work and describe the location of the building or work, which is why most offices can process a water heater permit as a short form rather than a full plan set (IRC R105.3).
  • Once a complete application is on file, the building official must act on it and issue the permit as soon as practicable if the proposed work conforms to code, which is the basis for the same-day or next-business-day turnaround many permit offices offer for a straight swap (IRC R105.3.1).
  • For Greenville County, the permit only stays valid if the work starts within the code's default window before it lapses, so scheduling the replacement and its inspection soon after the permit issues matters (IRC R105.5).

General submittal guidance from 2021 International Residential Code (IRC), Chapter 1, Section R105 (Permits). Source. Greenville County Building Safety (Planning and Code Compliance) sets the exact checklist for Greenville County.

Where to apply in Greenville County:

Greenville County Building Safety (Planning and Code Compliance)

Inspections and closing out your permit

In Greenville County, a water heater swap normally draws one inspection, a final, since the work is exposed rather than buried behind new framing. That single visit confirms the relief valve and its discharge pipe, thermal expansion control and seismic strapping where the installation requires them, and, on gas units, adequate combustion air and an approved vent connection.

  1. In Greenville County: the lifecycle has one required visit, the final inspection, made after the permitted work is complete and before the water heater goes into service; because a straight swap conceals nothing behind framing, offices typically do not schedule a separate rough-in visit for it (IRC R109.1.6).
  2. In Greenville County: the inspector confirms the water heater is protected by either a separate pressure relief valve and temperature relief valve, or one combination valve rated for the appliance (IRC P2804.1).
  3. In Greenville County: the relief valve's discharge pipe is checked for an unobstructed, un-trapped gravity path that ends through an air gap no more than 6 inches above the floor or pan, since a wrong discharge pipe is one of the most common reasons a water heater fails inspection (IRC P2804.6.1).
  4. In Greenville County: where the water heater feeds a closed system, for instance behind a backflow preventer or check valve, the inspector looks for a thermal expansion control device sized to absorb the resulting pressure increase (IRC P2903.4.2).
  5. In Greenville County: on a gas-fired unit, the inspector verifies the space provides enough combustion air, sized at 50 cubic feet per 1,000 Btu per hour of the appliance's input rating unless an engineered alternative method is used (IRC G2407.5.1).
  6. In Greenville County: the gas unit's vent must tie into an approved venting system, which the inspector checks along with the vent's physical connections and support (IRC G2427.1, G2427.2).
  7. In Greenville County: where site conditions call for them, the inspector also checks for a drain pan under a tank whose leakage would cause damage, and for seismic strapping in the upper and lower thirds of the tank in the seismic design categories and townhouse conditions where the code requires it (IRC P2801.6; P2801.8).

Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Greenville County permit portal or by phone at 864-467-7060.

Inspection sequence from 2021 International Residential Code (IRC), Chapters 24, 28, and 29 (Fuel Gas; Water Heaters; Water Supply and Distribution). Source. An open permit left un-inspected can surface later in a title search or home sale.

Permitting activity in Greenville County

In 2025, Greenville County authorized permits for 4,947 new residential housing units (4,222 single-family, 725 in multi-family buildings), valued at $2.0B, down from 5,575 the year before. That works out to about 8.5 permits per 1,000 residents.

Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 583,125.

Frequently asked questions

Do you need a water heater permit in Greenville County?
Greenville County requires a permit to replace a water heater, gas or electric. Its Answer Book says mechanical permits are required for new equipment and change-outs, and the county prices water heaters on its mechanical fee schedule, at $36.00 for gas and $12.00 for electric. The statewide exemption list at S.C. Code 40-59-265 has no water heater item. Always confirm with the Greenville County Building Safety (Planning and Code Compliance) before starting.
How much does a water heater permit cost in Greenville County?
Mechanical Permit Fees on the Residential Permit Fees schedule: Gas Water Heater $36.00 and Electric Water Heater $12.00, with a mechanical minimum fee per permit of $72.00. No effective date printed; the department's notice says residential permit fees rose 20 percent starting July 1, 2025. See the official fee schedule for current amounts.
How long does a water heater permit take in Greenville County?
Five-day processing period for permits to be issued, per the Building Safety notice (the Forms and Applications page notice still reads one to two weeks). Times can vary by workload and project scope, so confirm with the office.
Where do you apply for a water heater permit in Greenville County?
You can apply through the Greenville County permit portal or contact the Greenville County Building Safety (Planning and Code Compliance) directly. The links are listed on this page.
Can a homeowner pull a water heater permit themselves in Greenville County?
Under South Carolina law (S.C. Code Ann. 40-59-260(A), (B), (C), (E), (F); 40-59-265; 40-59-280; 40-59-20(6), (7); 40-59-30(A)): South Carolina licenses residential builders and residential specialty contractors under S.C. Code Title 40 Chapter 59, and 40-59-260 exempts the owner of record who builds for himself. The exemption applies only if the owner does the work himself, with his own employees, or with licensed contractors or registered entities, if the structure is intended for the owner's sole occupancy or occupancy by the owner's family and is not intended for sale or rent, and if the general public does not have access to it. The owner must personally appear and sign the building permit application, and the local permitting agency must hand over a disclosure statement whose statutory text reads in part: You must supervise the construction yourself. You may build or improve a one-family or two-family residence. The building must be for your own use and occupancy. It may not be built for sale or rent. The sale restriction is two years and is a presumption rather than a flat bar: 40-59-260(B) makes proof of sale or rent, or of offering for sale or rent, within two years after completion or issuance of a certificate of occupancy prima facie evidence that the project was undertaken for sale or rent, which forfeits the exemption and exposes the owner to the chapter's penalties. South Carolina then adds a step no other state in this wave has: 40-59-260(E) requires the owner to promptly record a notice with the register of deeds, indexed under the owner's name in the grantor index, stating that the building was constructed by the owner as an unlicensed builder, and failure to record revokes the statutory exemption. The exemption is from the licensing chapter, not from the permit, and 40-59-280 requires the building official to refuse a permit unless the applicant furnishes evidence of licensure, registration, or exemption. Confirm how Greenville County applies this before you apply.

From the Library

What else needs a permit in Greenville County

Every other permit type we have verified for this jurisdiction, with the rule that applies here.

ProjectPermit needed?ThresholdTypical fee
Bathroom Remodel PermitIt dependsBefore moving or adding plumbing fixtures, adding circuits or changing walls in a bathroom...cost of the project."), plus trade fees: plumbing minimum fee per permit $72.00 and...
Deck PermitIt dependsdeck area, for decks not more than 30 inches above grade at any point...work is priced on the Residential Permit Fees schedule by total valuation: "$1,000...
Electrical PermitIt dependsBefore any electrical work beyond minor repairs, including service upgrades, meter...Electrical Permit Fees: minimum fee per permit $72.00
EV Charger PermitIt dependsBefore installing a hardwired charger or a new 240-volt circuit or receptacle for an...Electrical Permit Fees: minimum fee per permit $72.00
Fence PermitIt dependsfence height...work is priced on the Residential Permit Fees schedule by total valuation: "$1,000...
HVAC PermitIt dependsBefore installing or changing out heating or cooling equipment, adding ductwork, or...Mechanical Permit Fees: minimum fee per permit $72.00
Plumbing PermitIt dependsBefore adding or relocating plumbing fixtures, replacing concealed pipe, or connecting...Plumbing Permit Fees: minimum fee per permit $72.00
Pool PermitIt dependsprefabricated swimming pools only...work is priced on the Residential Permit Fees schedule by total valuation: "$1,000...
Roof Replacement PermitPermit requiredAny sizeFlat fee: the Residential Roofing Permit line is $108.00 under Miscellaneous Permit Fees...
Shed PermitIt dependsfloor area of a one-story detached accessory structure...work is priced on the Residential Permit Fees schedule by total valuation: "$1,000...
Solar PermitPermit requiredAny sizeElectrical schedule line Solar Panel per 5kw at $48.00, with the electrical minimum fee...

Everything above, sourced

Code references

National and state model-code sections the general guidance on this page is drawn from. They are not Greenville County documents; the office above sets the local rules.

How this water heater permit page for Greenville County was verified. 2 official sources: greenvillecountysc.gov, greenvillecountysc.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with Greenville County Building Safety (Planning and Code Compliance). Rules change; confirm before you build. How we verify.

Last checked: Report an error on this page

Compare Water Heater Permit requirements across South Carolina localities

Water heater permit rules nationwide

Look up an existing Greenville County permit record

Permit required
Get quotes