South Carolina / Greenville County
EV Charger Permit in Greenville County, South Carolina
It depends
Sometimes, depending on the project
Before installing a hardwired charger or a new 240-volt circuit or receptacle for an electric vehicle.
Issued byGreenville County Building Safety (Planning and Code Compliance)
By Mario Bailey, verified against official sources
Quick answer
Greenville County publishes no residential EV charger rule; its only EV document is a Commercial Electric Vehicle Charging Stations form. The electrical rule decides it: the county says all electrical work requires a permit, and the statewide exemption at S.C. Code 40-59-265 covers only minor work such as connecting approved portable electrical equipment to approved permanently installed receptacles. So plugging a portable charger into an existing outlet needs no permit, while a new circuit, a new 240-volt receptacle or a hardwired wall charger needs a county electrical permit.
Who is pulling this permit?
Apply yourself
Hire it out
Sponsored
A licensed electrician typically pulls the electrical permit as part of the install. If you have not picked one yet, compare a few quotes first.
Compare electrician quotes on Angi
Sponsored link. PermitNotebook may earn a fee if you request quotes through it. Partners never influence our permit data.
When a permit is usually needed
Before installing a hardwired charger or a new 240-volt circuit or receptacle for an electric vehicle.
What an EV charger permit costs in Greenville County
How to apply in Greenville County
In Greenville County, in most of the US, installing a Level 2 (240 volt) home EV charger is handled as an electrical permit built around a load calculation and a single line diagram showing the new dedicated circuit. A Level 1 charger that simply plugs into an existing 120 volt outlet typically needs no permit unless new wiring is added.
What most EV charger permit applications include:
- For Greenville County, a Level 2 charger needs its own dedicated 240 volt circuit and requires an electrical permit with inspection, since each outlet installed for EV charging must be fed by an individual branch circuit with no other outlets on it (NEC 625.40).
- For Greenville County, the application includes an electrical load calculation showing the existing service panel has enough spare capacity for the added EVSE demand, worked out using the standard dwelling load calculation method (NEC 220.83).
- For Greenville County, the breaker or other overcurrent device feeding the charger must be sized for continuous duty, rated at not less than 125 percent of the equipment's maximum load (NEC 625.41).
- Plan submittal typically includes a single line diagram showing conductor size, breaker size, conduit, and panel rating, plus the charger's manufacturer specifications, since the EVSE itself must be a listed product (NEC 625.5).
- For charging equipment rated over 60 amps or over 150 volts to ground, the application has to show a disconnecting means installed in a readily accessible location and capable of being locked open (NEC 625.43).
- For Greenville County, the charger must be shown connected and fastened in place according to the manufacturer's installation instructions, whether it is hardwired or a plug in unit on a dedicated receptacle (NEC 625.44).
General submittal guidance from National Electrical Code (NFPA 70), Article 625 Electric Vehicle Charging System and Article 220 Load Calculations, 2017 to 2023 editions. Source. Greenville County Building Safety (Planning and Code Compliance) sets the exact checklist for Greenville County.
Where to apply in Greenville County:
Greenville County Building Safety (Planning and Code Compliance)
- 301 University Ridge, Greenville County Square, Suite S-3100, Greenville, SC 29601
- Phone: 864-467-7060
- Email: permits@greenvillecounty.org
Inspections and closing out your permit
In Greenville County, a Level 2 EV charger installation gets a rough wiring inspection if any new conductors will be hidden inside walls, ceilings, or run underground, then a final inspection that checks the dedicated circuit, breaker sizing, any required GFCI protection, the disconnect, and the charger's listing before the permit closes.
- In Greenville County: if new EVSE conductors will be concealed in a wall or ceiling, or run underground, they must pass a rough wiring inspection before being covered, since that inspection confirms the dedicated branch circuit required for the charger (NEC 625.40).
- In Greenville County: at final inspection, the breaker or other overcurrent device serving the charger is checked to confirm it is properly rated for the continuous EV charging load (NEC 625.41).
- In Greenville County: any receptacle installed for EV charging, as opposed to a hardwired connection, has to be checked for ground fault circuit interrupter protection (NEC 625.54).
- In Greenville County: where the EVSE is rated over 60 amps or 150 volts to ground, the inspector confirms a lockable, readily accessible disconnecting means was installed (NEC 625.43).
- In Greenville County: the inspector verifies the charger, along with its fittings and associated equipment, carries a nationally recognized testing laboratory listing (NEC 625.5).
- In Greenville County: mounting height is checked against the manufacturer's instructions, with the coupling means generally required to sit at least 18 inches above an indoor floor or 24 inches above outdoor grade unless the equipment is listed otherwise (NEC 625.50).
Schedule each inspection in advance and pass the final before you use the work or close the permit. Request inspections through the Greenville County permit portal or by phone at 864-467-7060.
Inspection sequence from National Electrical Code (NFPA 70), Article 625 Electric Vehicle Charging System, 2017 to 2023 editions. Source. An open permit left un-inspected can surface later in a title search or home sale.
Your EV Charger Permit checklist for Greenville County
- Confirm the requirement. Sometimes, depending on the project. Usually needed: Before installing a hardwired charger or a new 240-volt circuit or receptacle for an electric vehicle.
- Budget the fee. No EV charger line item on the residential schedule. Electrical Permit Fees: minimum fee per permit $72.00; New No. of Circuits and Service Change No. of Circuits $3.60 per circuit; a service change is $0.36 per amp (100-amp minimum). No effective date printed. Official fee schedule.
- Apply. In Greenville County, in most of the US, installing a Level 2 (240 volt) home EV charger is handled as an electrical permit built around a load calculation and a single line diagram showing the new dedicated circuit. A Level 1 charger that simply plugs into an existing 120 volt outlet typically needs no permit unless new wiring is added. Start at the Greenville County permit portal.
- Keep the office details handy. Greenville County Building Safety (Planning and Code Compliance). Phone: 864-467-7060. Address: 301 University Ridge, Greenville County Square, Suite S-3100, Greenville, SC 29601.
- Plan for inspections. In Greenville County, a Level 2 EV charger installation gets a rough wiring inspection if any new conductors will be hidden inside walls, ceilings, or run underground, then a final inspection that checks the dedicated circuit, breaker sizing, any required GFCI protection, the disconnect, and the charger's listing before the permit closes.
Compiled from the official sources on this page. Last checked .
Permitting activity in Greenville County
In 2025, Greenville County authorized permits for 4,947 new residential housing units (4,222 single-family, 725 in multi-family buildings), valued at $2.0B, down from 5,575 the year before. That works out to about 8.5 permits per 1,000 residents.
Source: U.S. Census Bureau, Building Permits Survey, 2025 annual data · population 583,125.
Frequently asked questions
- Do you need an EV charger permit in Greenville County?
- Greenville County publishes no residential EV charger rule; its only EV document is a Commercial Electric Vehicle Charging Stations form. The electrical rule decides it: the county says all electrical work requires a permit, and the statewide exemption at S.C. Code 40-59-265 covers only minor work such as connecting approved portable electrical equipment to approved permanently installed receptacles. So plugging a portable charger into an existing outlet needs no permit, while a new circuit, a new 240-volt receptacle or a hardwired wall charger needs a county electrical permit. Always confirm with the Greenville County Building Safety (Planning and Code Compliance) before starting.
- How much does an EV charger permit cost in Greenville County?
- No EV charger line item on the residential schedule. Electrical Permit Fees: minimum fee per permit $72.00; New No. of Circuits and Service Change No. of Circuits $3.60 per circuit; a service change is $0.36 per amp (100-amp minimum). No effective date printed. See the official fee schedule for current amounts.
- How long does an EV charger permit take in Greenville County?
- Five-day processing period for permits to be issued, per the Building Safety notice (the Forms and Applications page notice still reads one to two weeks). Times can vary by workload and project scope, so confirm with the office.
- Where do you apply for an EV charger permit in Greenville County?
- You can apply through the Greenville County permit portal or contact the Greenville County Building Safety (Planning and Code Compliance) directly. The links are listed on this page.
- Can a homeowner pull an EV charger permit themselves in Greenville County?
- Under South Carolina law (S.C. Code Ann. 40-59-260(A), (B), (C), (E), (F); 40-59-265; 40-59-280; 40-59-20(6), (7); 40-59-30(A)): South Carolina licenses residential builders and residential specialty contractors under S.C. Code Title 40 Chapter 59, and 40-59-260 exempts the owner of record who builds for himself. The exemption applies only if the owner does the work himself, with his own employees, or with licensed contractors or registered entities, if the structure is intended for the owner's sole occupancy or occupancy by the owner's family and is not intended for sale or rent, and if the general public does not have access to it. The owner must personally appear and sign the building permit application, and the local permitting agency must hand over a disclosure statement whose statutory text reads in part: You must supervise the construction yourself. You may build or improve a one-family or two-family residence. The building must be for your own use and occupancy. It may not be built for sale or rent. The sale restriction is two years and is a presumption rather than a flat bar: 40-59-260(B) makes proof of sale or rent, or of offering for sale or rent, within two years after completion or issuance of a certificate of occupancy prima facie evidence that the project was undertaken for sale or rent, which forfeits the exemption and exposes the owner to the chapter's penalties. South Carolina then adds a step no other state in this wave has: 40-59-260(E) requires the owner to promptly record a notice with the register of deeds, indexed under the owner's name in the grantor index, stating that the building was constructed by the owner as an unlicensed builder, and failure to record revokes the statutory exemption. The exemption is from the licensing chapter, not from the permit, and 40-59-280 requires the building official to refuse a permit unless the applicant furnishes evidence of licensure, registration, or exemption. Confirm how Greenville County applies this before you apply.
From the Library
What else needs a permit in Greenville County
Every other permit type we have verified for this jurisdiction, with the rule that applies here.
| Project | Permit needed? | Threshold | Typical fee |
|---|---|---|---|
| Bathroom Remodel Permit | It depends | Before moving or adding plumbing fixtures, adding circuits or changing walls in a bathroom | ...cost of the project."), plus trade fees: plumbing minimum fee per permit $72.00 and... |
| Deck Permit | It depends | deck area, for decks not more than 30 inches above grade at any point | ...work is priced on the Residential Permit Fees schedule by total valuation: "$1,000... |
| Electrical Permit | It depends | Before any electrical work beyond minor repairs, including service upgrades, meter... | Electrical Permit Fees: minimum fee per permit $72.00 |
| Fence Permit | It depends | fence height | ...work is priced on the Residential Permit Fees schedule by total valuation: "$1,000... |
| HVAC Permit | It depends | Before installing or changing out heating or cooling equipment, adding ductwork, or... | Mechanical Permit Fees: minimum fee per permit $72.00 |
| Plumbing Permit | It depends | Before adding or relocating plumbing fixtures, replacing concealed pipe, or connecting... | Plumbing Permit Fees: minimum fee per permit $72.00 |
| Pool Permit | It depends | prefabricated swimming pools only | ...work is priced on the Residential Permit Fees schedule by total valuation: "$1,000... |
| Roof Replacement Permit | Permit required | Any size | Flat fee: the Residential Roofing Permit line is $108.00 under Miscellaneous Permit Fees... |
| Shed Permit | It depends | floor area of a one-story detached accessory structure | ...work is priced on the Residential Permit Fees schedule by total valuation: "$1,000... |
| Solar Permit | Permit required | Any size | Electrical schedule line Solar Panel per 5kw at $48.00, with the electrical minimum fee... |
| Water Heater Permit | Permit required | Any size | ...Permit Fees on the Residential Permit Fees schedule: Gas Water Heater $36.00 and... |
Everything above, sourced
Code references
National and state model-code sections the general guidance on this page is drawn from. They are not Greenville County documents; the office above sets the local rules.
How this EV charger permit page for Greenville County was verified. 2 official sources: greenvillecountysc.gov, scstatehouse.gov; fee schedule: official document. Last checked by Mario Bailey, not confirmed with Greenville County Building Safety (Planning and Code Compliance). Rules change; confirm before you build. How we verify.
Last checked: Report an error on this page
Compare EV Charger Permit requirements across South Carolina localities