Building without a permit in Wyoming
Quick answer
Wyoming has no statewide building permit for one- and two-family homes, so there is no state crime of building a house without one, though wiring new construction without a state electrical wiring permit, where the state has jurisdiction, is a state misdemeanor. Building permits for houses come from city, town, and county codes, and the penalty comes from the local ordinance under a state cap: a city or town may enforce its ordinances with fines up to $750, up to 6 months in jail, or both (W.S. 15-1-103(a)(xli)), and may prescribe how buildings are built and order removal of a building built in violation of an ordinance (W.S. 15-1-103(a)(xxv), (xxvii)).
- Who sets the penalty
- Cities and counties, under a state cap
- Fine in state law
- Cities and county zoning up to $750
- Jail in state law
- Yes, up to 6 months (city ordinances)
- Each day a new offense
- Yes (county zoning)
- Permit after the fact
- Path in state law
What Wyoming law says
Wyoming has no statewide building permit for one- and two-family homes, so there is no state crime of building a house without one, though wiring new construction without a state electrical wiring permit, where the state has jurisdiction, is a state misdemeanor. Building permits for houses come from city, town, and county codes, and the penalty comes from the local ordinance under a state cap: a city or town may enforce its ordinances with fines up to $750, up to 6 months in jail, or both (W.S. 15-1-103(a)(xli)), and may prescribe how buildings are built and order removal of a building built in violation of an ordinance (W.S. 15-1-103(a)(xxv), (xxvii)).
In unincorporated areas with county zoning, it is unlawful to erect, construct, enlarge, or change a building without first getting a county zoning certificate, and each violation carries a fine of up to $750 (W.S. 18-5-203, 18-5-206), with each day a separate offense for violating an adopted zoning resolution (W.S. 18-5-204). The state's own exposure is electrical: wiring a new build or a remodel that needs the utility to connect or disconnect power without a state electrical wiring permit, where the state has jurisdiction, violates W.S. 35-9-120(e), a misdemeanor punishable by a fine of up to $500, up to 6 months in jail, or both for an individual, and up to $1,000 for a corporation (W.S. 35-9-130(a)).
Cited from W.S. 15-1-103(a)(xli), (xxv), (xxvii); 18-5-203; 18-5-204; 18-5-206; 35-9-120(e); 35-9-130(a): official text. Localities enforce these rules and may add their own fees and procedures on top.
Can you get a permit after the work is done?
No Wyoming statute creates a general after-the-fact or as-built permit for a house; legalizing unpermitted work is handled under each city's or county's own code. State law gives cities the power to cause the destruction or removal of any building constructed or repaired in violation of an ordinance, and to provide for the repair, removal, or destruction of dangerous buildings (W.S. 15-1-103(a)(xxvi), (xxvii)).
County zoning resolutions can be enforced by injunction, mandamus, or abatement in addition to fines (W.S. 18-5-205). For the state electrical program, a civil penalty for using unlicensed labor is not enforceable if the violation is cured or appealed within 60 days of the notice of violation (W.S. 35-9-130(c)). The State Fire Marshal's stop-work power for work begun without approved plans (W.S. 35-9-108(k)) applies to public and state buildings, not to private houses.
Cited from W.S. 15-1-103(a)(xxvi), (xxvii); 18-5-205; 35-9-130(c); 35-9-108(a), (k): official text.
The typical path, whatever your locality calls it: stop any ongoing work, contact the permit office before they contact you, apply for the permit describing what was actually built, and expect the office to require opening up or inspecting concealed work. Voluntarily coming forward generally goes better than waiting for a complaint or a sale to surface it.
What Wyoming permit offices charge when work starts first
The statute above sets the ceiling; the bill comes from the local office. One Wyoming jurisdiction we cover publishes a specific surcharge for work started before the permit, quoted here from the fee schedule or permit page we verified, each linked to the page that carries the citation.
-
Work begun before the permit is issued carries an investigation fee equal to the permit fee (IRC R108.6 as amended by 15.10.020(H)).
Cheyenne · from the bathroom remodel permit page · last checked
Jurisdictions not listed either publish no surcharge clause or publish one we could not quote from an official schedule; their permit pages state what we could verify.
What Cheyenne and Laramie add when the work came first
Laramie and Casper charge for starting first just as Cheyenne, quoted above, does. Cheyenne and Laramie add an investigation fee equal to the permit fee, on top of it, and in Cheyenne it is owed whether or not a permit is ever obtained; Casper doubles the building permit fee for an after-the-fact permit. Worked below for the same finished basement in Cheyenne and Laramie.
- Cheyenne's current fee schedule lists, for work valued at $29,001 to $30,000, a permit fee of $442.25, a plan review fee of $287.46 and a total of $729.71. cheyennecity.org: fee schedule
- Anyone who starts work before Cheyenne issues the permit owes an investigation fee equal to the permit fee. library.municode.com: code of ordinances
- Cheyenne's contractor licensing regulations add that the investigation fee for work done or ordered without a required permit is owed whether or not a permit is later obtained. cheyennecity.org: contractor licensing board rules and regs 3.10.26
- Laramie's Building Permit and Plan Review Fee Schedule, the one its building page links today, is Informational Bulletin #25 dated November 2017, effective January 1, 2006. cityoflaramie.org: 25 Building Permit Plan Review Fee Schedule
- Laramie charges an investigation fee for work done without a permit equal to, and in addition to, the required permit fee. cityoflaramie.org: 25 Building Permit Plan Review Fee Schedule
- Laramie's building permit fee for work valued at $29,001 to $30,000 is $441.75, with a plan review fee of $287.14. cityoflaramie.org: 25 Building Permit Plan Review Fee Schedule
- Laramie charges plan review whenever the work is valued over $5,000.00, due when the application and plans are submitted. cityoflaramie.org: Getting a Building Permit
- Plumbing, mechanical and electrical work need separate Laramie permits with their own fee schedules. cityoflaramie.org: 25 Building Permit Plan Review Fee Schedule
- Casper assesses double the building permit fee for after-the-fact permits, meaning construction started before a complete building permit application was reviewed and approved. casperwy.gov: Current Fee Schedule February 2, 2026
- Laramie values work at its current replacement cost, counting all materials and labor, with an estimate of labor even when the work was done at no cost. cityoflaramie.org: 25 Building Permit Plan Review Fee Schedule
Cheyenne, a basement finished without a permit, valued at $29,001 to $30,000
| Permit fee | $442.25 |
| Plan review fee | $287.46 |
| Investigation fee, equal to the permit fee | $442.25 |
| Finished first | $1,171.96 |
Reinspections cost extra, and a Cheyenne permit can include the electrical and mechanical work, so value the whole job.
Laramie, the same basement
| Building permit fee | $441.75 |
| Plan review fee | $287.14 |
| Investigation fee, equal to and in addition to the permit fee | $441.75 |
| Finished first | $1,170.64 |
Plumbing, mechanical and electrical permits are separate in Laramie, and its schedule is the older one the city still links, so confirm the figures when you call.
Before you call
Work out the project's value the way the city will, with receipts for materials and labor, and count your own labor at what a contractor would charge, since Laramie values the work at replacement cost, labor included. Photograph everything before it is opened. Then ask: "This work at (your address) was done before a permit. Will the investigation fee equal the permit fee, and what has to be uncovered for inspection?"
Fines, permit bans and how to apply in Wyoming's cities
Laramie's citations step up with repeat offenses, it can prosecute instead under its general penalty with each day a separate offense, and it can bar a repeat offender from new permits; Cheyenne and Casper treat violations as misdemeanors. In each city the fix starts with an application.
- Laramie can cite work without a permit into municipal court with fines of $50 for a first offense, $250 for a second within 5 years and $750 for a third or later within 5 years, not counting court costs. cityoflaramie.org: 1524 Buildings and Construction 11182025
- Anyone with 3 violations for working without a permit in 12 months is barred from new Laramie permits for 6 months and loses existing ones, subject to appeal to the Building and Fire Code Board of Appeals. cityoflaramie.org: 1524 Buildings and Construction 11182025
- Laramie can also prosecute a violation of its building chapter under the city's general penalty, besides or instead of a citation. cityoflaramie.org: 1524 Buildings and Construction 11182025
- Laramie's general penalty is a fine of not more than seven hundred fifty dollars, and each day a violation continues is a separate offense. library.municode.com: code of ordinances
- Cheyenne's residential code sends violation penalties to the city's general penalty section, 1.24.010. library.municode.com: code of ordinances
- Under Cheyenne's general penalty, a violation is a misdemeanor punishable by a fine of up to $750.00 plus costs, up to six months in jail, or both, and each day it continues is a separate offense. library.municode.com: code of ordinances
- A Casper code violation with no specific penalty is a misdemeanor punishable by a fine of not more than seven hundred fifty dollars, plus court costs of no more than ten dollars. library.municode.com: code of ordinances
- Casper requires a permit before building a new building or addition or remodeling, altering or repairing any existing structure in the city. casperwy.gov: permit requirements
- Laramie names finishing a basement and building a garage or deck among the projects that need a building permit. cityoflaramie.org: Getting a Building Permit
- For an interior remodel or basement finish with no exterior changes, Cheyenne asks for digital plans with room dimensions and uses, an online residential permit application and REScheck energy calculations; fees are paid at submittal and the process takes about 5-6 business days. cheyennecity.org: res interior remodel and basement finish
- Cheyenne's Building Division takes all permit applications and inspection requests online through its OpenGov portal. cheyennecity.org: Building Permitting Licensing
- In Cheyenne a homeowner may pull the permit only for an owner-occupied one-family home, by signing a notarized form swearing the work is not for resale or rental for at least three years and accepting personal responsibility, including prosecution, for code violations not corrected as ordered. cheyennecity.org: homeowner as contractor form
- Casper issues permits to licensed contractors and to homeowners working on their primary residence, priced on the value of materials and labor; a permit is good for 180 days. casperwy.gov: permit requirements
- Casper's Building Inspection Division takes permits at building@casperwy.gov or (307) 235-8254 and recommends applying through its CSS online portal. casperwy.gov: permit requirements
- Laramie building and trade permits are applied for only through the city's Civic Access web portal; help is at 307-721-5271 or codeadmin@cityoflaramie.org. cityoflaramie.org: Building Permits and Informational Bulle
Selling a Wyoming house with unpermitted work
Wyoming requires a seller's disclosure statement only for vacant land, so for a house the statutory duty to disclose known adverse material facts, including the property's physical condition, falls on the licensed agents.
- Wyoming's property disclosure statement under W.S. 34-1-151(a) is required only from sellers of vacant land: land with no habitable dwelling, outside a platted subdivision, city or town, and under 140 acres. wyoleg.gov: title34
- A seller's real estate agent in Wyoming must disclose to any prospective buyer all adverse material facts the agent actually knows, including the property's physical condition and material defects, but need not inspect the property or verify the seller's statements. wyoleg.gov: title33
- A buyer's agent must disclose to the buyer the adverse material facts the agent actually knows. wyoleg.gov: title33
- Cheyenne residential permits applied for after 2009 can be searched in the OpenGov portal by address or parcel ID. cheyennecity.org: Building Permitting Licensing
Before you list
Search the permit record for your address (Cheyenne's covers permits applied for after 2009) and set it beside the work done while you owned the house. Legalize what is missing before you list: an agent who knows of an adverse material fact has to disclose it, so if your agent knows, the buyer will be told.
If your contractor skipped the permit
Wyoming has no state contractor license, but Cheyenne and Casper license contractors and require them to pull the permit before work starts, which gives you a complaint to file with the city.
- Contractors licensed by Cheyenne must obtain all required permits before any work is performed. cheyennecity.org: contractor licensing board rules and regs 3.10.26
- Casper requires its licensed contractors to obtain any required permit before work starts, except for emergency repairs, which must be permitted by the end of the next business day. library.municode.com: code of ordinances
- Failing to obtain required permits before starting work is grounds for Casper to suspend or revoke a contractor's license. library.municode.com: code of ordinances
- Cheyenne's Contractor Licensing Board may suspend, revoke or put on probation a licensee proven to have violated the city's building title or the licensing regulations. cheyennecity.org: contractor licensing board rules and regs 3.10.26
- A homeowner starts discipline by filing a written Contractor Complaint on the Board's form within one year of the violation or its discovery, and never more than three years after the work. cheyennecity.org: contractor licensing board rules and regs 3.10.26
- Any Casper resident can file a written complaint against a licensed contractor on the department's form, within sixty days of discovering the violation. library.municode.com: code of ordinances
- The Attorney General's Consumer Protection and Antitrust Unit accepts written consumer complaints and may forward them to the business for a written response, but cannot act as a consumer's private attorney. ag.wyo.gov: consumer protection and antitrust unit
- The unit says it will not examine private contractual disputes, and asks consumers to try resolving the problem with the business first. ag.wyo.gov: consumer complaints
- The Consumer Protection and Antitrust Unit can be reached at (307) 777-6397 or (307) 777-8962 and ag.consumer@wyo.gov. ag.wyo.gov: consumer protection and antitrust unit
- Under the Wyoming Consumer Protection Act, a consumer who relied on an uncured unlawful deceptive trade practice can sue for the damages actually suffered. wyoleg.gov: title40
- Before suing under the Act, the consumer must give the business written notice within one year of discovering the practice or two years after the transaction, whichever comes first. wyoleg.gov: title40
What to send the contractor first
"A licensed contractor in this city has to obtain the permit before work starts, and none was obtained for the job at (your address). Please apply now and arrange the inspections, or answer in writing." Casper gives you sixty days from discovery to complain, so do not wait on the reply.
Who can pull the permit
For electrical work, yes. The rule that licensed electrical contractors must install all electrical equipment is waived for property owned or leased by a person when that person, a partner, or a major stockholder of a family corporation installs the equipment and the property is not for immediate resale (W.S. 35-9-123(a)(i)). The waiver does not exempt the owner from code requirements, and it does not cover anyone who contracts for the exempt owner (W.S. 35-9-123(a), (b)).
The owner still needs a state wiring permit where W.S. 35-9-120(e) applies; the Department of Fire Prevention and Electrical Safety issues homeowner wiring permits through its online portal. Whether a homeowner may pull their own building permit, and on what terms, is set by the city or county code; no state owner-builder statute or disclosure form was found.
Cited from W.S. 35-9-123(a)(i), (b); 35-9-120(e): official text.
Common questions about unpermitted work in Wyoming
- What is the penalty for building without a permit in Wyoming?
- Wyoming has no statewide building permit for one- and two-family homes, so there is no state crime of building a house without one, though wiring new construction without a state electrical wiring permit, where the state has jurisdiction, is a state misdemeanor. Building permits for houses come from city, town, and county codes, and the penalty comes from the local ordinance under a state cap: a city or town may enforce its ordinances with fines up to $750, up to 6 months in jail, or both (W.S. 15-1-103(a)(xli)), and may prescribe how buildings are built and order removal of a building built in violation of an ordinance (W.S. 15-1-103(a)(xxv), (xxvii)). (W.S. 15-1-103(a)(xli), (xxv), (xxvii); 18-5-203; 18-5-204; 18-5-206; 35-9-120(e); 35-9-130(a))
- Can you get a permit after the work is done in Wyoming?
- No Wyoming statute creates a general after-the-fact or as-built permit for a house; legalizing unpermitted work is handled under each city's or county's own code. State law gives cities the power to cause the destruction or removal of any building constructed or repaired in violation of an ordinance, and to provide for the repair, removal, or destruction of dangerous buildings (W.S. 15-1-103(a)(xxvi), (xxvii)). (W.S. 15-1-103(a)(xxvi), (xxvii); 18-5-205; 35-9-130(c); 35-9-108(a), (k))
- Who can pull a permit in Wyoming?
- For electrical work, yes. The rule that licensed electrical contractors must install all electrical equipment is waived for property owned or leased by a person when that person, a partner, or a major stockholder of a family corporation installs the equipment and the property is not for immediate resale (W.S. 35-9-123(a)(i)). (W.S. 35-9-123(a)(i), (b); 35-9-120(e))
Related situations in Wyoming
- A stop work order was posted: what it means and how to lift it
- How to find out if a permit was pulled, or report work with none
- A wall was removed without a permit
- Selling a house with unpermitted work
- Buying a house with unpermitted work
See which parts of the work needed a permit, then send us the details
Want help getting unpermitted work approved?
Tell us where your project stands. Where we have a vetted local pro who handles permits in Wyoming, we connect you; otherwise we reply with the exact steps and office links for your situation. Free to ask; no obligation.
PermitNotebook is not a government agency and does not file permits. This is a free referral request; we may earn a fee if you hire a pro we introduce. Partners never influence our permit data. Privacy policy.
Your local permit office
Enforcement, after-the-fact fees, and the exact fix-it process are local. We cover these Wyoming permit offices:
Official sources
This page summarizes state law from the official sources listed above, with a last checked date. It is not legal advice. Penalties and procedures are applied by local offices and courts case by case; for anything contested or high stakes, confirm with your permit office or a licensed professional in Wyoming.