West Virginia has a State Building Code (legislative rule 87CSR4, adopted by the State Fire Commission under W. Va. Code 15A-11-5), but it only has force in the counties and cities that choose to adopt it, and the adopting local jurisdiction enforces it. Where it applies, W. Va. Code 15A-10-22(a) makes violating any rule promulgated by the State Fire Commission a misdemeanor punishable by a fine of up to $100, up to 90 days in county jail, or both, and each day illegal construction or alteration continues after the person knows or is officially notified that it is illegal counts as a separate offense.
- Who sets the penalty
- State lawApplies only where the county or city adopted the state code
- Fine in state law
- Up to $100 (misdemeanor)
- Jail in state law
- Yes, up to 90 days
- Each day a new offense
- Yes, after notice
- Permit after the fact
- Path in state law
What West Virginia law says
West Virginia has a State Building Code (legislative rule 87CSR4, adopted by the State Fire Commission under W. Va. Code 15A-11-5), but it only has force in the counties and cities that choose to adopt it, and the adopting local jurisdiction enforces it. Where it applies, W. Va. Code 15A-10-22(a) makes violating any rule promulgated by the State Fire Commission a misdemeanor punishable by a fine of up to $100, up to 90 days in county jail, or both, and each day illegal construction or alteration continues after the person knows or is officially notified that it is illegal counts as a separate offense.
Cities also get their own tools: W. Va. Code 8-12-14 lets every municipality require a permit before any structure is built, repaired or altered, and 8-11-1 lets it set fines and up to 30 days in jail for ordinance violations and sue in circuit court for an injunction. Where neither the county nor the city has adopted the code, state law sets no building permit requirement and no permit penalty.
Cited from W. Va. Code 15A-10-22(a); 15A-11-5(a), (d); 8-12-14; 8-11-1(a)(2), (c); 7-1-3n; 87CSR4: official text. Localities enforce these rules and may add their own fees and procedures on top.
Can you get a permit after the work is done?
No West Virginia statute creates an after-the-fact permit, but the State Building Code does provide for a work-before-permit fee. Rule 87CSR4 gives the adopted ICC codes the same force as if printed in the rule, and it adopts the 2018 IRC and IBC with amendments that leave their administrative Chapter 1 in place, so IRC R108.6 and IBC 109.4 (work commencing before permit issuance) are part of the State Building Code. Those sections subject anyone who starts permit-required work before getting the permit to an extra fee, on top of the regular permit fee; IRC R108.6 leaves the amount to the applicable governing authority and IBC 109.4 to the building official, so either way it is set locally.
The amount, and the steps to legalize the work (an after-the-fact permit, opening walls for inspection), come from the adopting county or city, which enforces the code (15A-11-5(d)). State law also lets a city sue in circuit court to compel compliance (8-11-1(c)) and adopt ordinances ordering unsafe structures repaired, closed or demolished (8-12-16).
Cited from 87CSR4-4.1, 4.1.a, 4.1.h (adopting 2018 IRC R108.6 and 2018 IBC 109.4); W. Va. Code 15A-11-5(d); 8-11-1(c); 8-12-16: official text.
The typical path, whatever your locality calls it: stop any ongoing work, contact the permit office before they contact you, apply for the permit describing what was actually built, and expect the office to require opening up or inspecting concealed work. Voluntarily coming forward generally goes better than waiting for a complaint or a sale to surface it.
What unincorporated Berkeley County, Charleston and Morgantown charge when the work came first
Berkeley County's permit application covers the unincorporated county only, not Martinsburg, Hedgesville or other incorporated towns. The county adds a flat investigation fee, Charleston doubles the fee for contractors and suspends their city license, and Morgantown charges an administrative fee once it issues a stop work order. Charleston and Morgantown set their fees in separate schedules, so ask either office for the figure; the worked examples are Berkeley County's. Two state rules frame all of it: a county or city code reaches only work done after that county or city adopted it, and buildings used primarily for agriculture are exempt.
- Berkeley County's permit application covers property in the unincorporated county only, not property within incorporated areas such as the City of Martinsburg or the City of Hedgesville. berkeleywv.org: 170
- Berkeley County's building permit fee schedule lists an Investigation Fee of $236.00 for work started without a permit, under its inspection fees. berkeleywv.org: Other Fee Schedule PDF
- The Berkeley County fee schedule carries revision dates of 5/17/12, 6/1/17 and 4/18/24. berkeleywv.org: Other Fee Schedule PDF
- For residential storage buildings over 200 sq ft, garages, porches, decks and barns, Berkeley County charges $41.00 plus .14 per square foot. berkeleywv.org: Other Fee Schedule PDF
- In the City of Charleston, contractors who start work before getting a permit pay a minimum $100 fee or twice the normal permit fee, whichever is greater, and face at least a 3-month suspension of their city license. charlestonwv.gov: permits
- Charleston assesses construction permit fees from its Schedule of Permit Fees and waives them when the total job cost is $2,500.00 or less; jobs over $10,000.00 without an existing contract need a Contract Certification. charlestonwv.gov: permits
- Morgantown's code (Sec. 1705.09) makes the owner, contractor and workers who build without a permit guilty of a violation punished under the general penalty section, adds an administrative fee if a stop work order is issued (the code's figure is $75.00, but the city's newer fee schedule sets that charge by project value, so ask for the current amount), and fines anyone who ignores a stop work order $100.00 to $500.00 per offense, each day a separate offense. library.municode.com: code of ordinances
- Morgantown's code sets building permit fees by reference to the city's current Plan Review and Permitting Fee Schedule rather than in the code itself. library.municode.com: code of ordinances
- The county's short form says a deck larger than 20 square feet needs an electrical receptacle. berkeleywv.org: 170
- Berkeley County's electrical inspections are done by approved third-party inspectors, whose separate fee is paid directly to the inspector. berkeleywv.org: 170
- Berkeley County charges extra trip fees for premature inspection requests, incomplete work or inaccessible work areas: $50.00 for the first trip, $75.00 for the second extra trip and $100.00 for the third. berkeleywv.org: Other Fee Schedule PDF
- A county or city may adopt the State Building Code only prospectively, not retroactively, so its code reaches work done after it was adopted. code.wvlegislature.gov: 15A 11 5
- Buildings used primarily for agricultural purposes are exempt from the State Building Code and from any county or city building code. code.wvlegislature.gov: 15A 11 5
Unincorporated Berkeley County, a 16 by 20 foot deck (320 square feet) permitted before it is built
| Deck permit, base | $41.00 |
| Deck permit, 320 sq ft at .14 | $44.80 |
| Permitted first | $85.80 |
Unincorporated Berkeley County, the same deck built without a permit
| Deck permit, base | $41.00 |
| Deck permit, 320 sq ft at .14 | $44.80 |
| Investigation fee, work started without a permit | $236.00 |
| Built first | $321.80 |
A deck this size needs an electrical receptacle, so the third-party electrical inspector's separate fee is added, and extra inspection trips cost $50.00, then $75.00, then $100.00.
Before you call
Measure what was built, since Berkeley County prices decks, garages and porches by the square foot, and photograph it. Then ask the permit office: "Work was done at (your address) before a permit. What plans will you need to see, and will the investigation fee apply?"
Stop work orders and fines in Berkeley County, Charleston and Morgantown
Charleston and Morgantown count each day a violation continues as a separate offense, and Morgantown's code reaches the owner of the building as well as the builder. In unincorporated Berkeley County, no work, not even digging, may start before the permit.
- Berkeley County's short-form application for decks, garages and storage buildings states that no work, including excavation or digging, may begin before a building permit is issued. berkeleywv.org: 170
- Charleston's code (Sec. 14-35) makes it unlawful to build, alter or occupy any building contrary to the city building code, or to allow such a violation. library.municode.com: code of ordinances
- Unless another penalty applies, a Charleston code violation is punishable by a fine of $10.00 to $500.00, up to 30 days in jail, or both, with each day of a continuing violation a separate offense; continuing violations can also be stopped by injunction. library.municode.com: code of ordinances
- Morgantown's Building Official can order all work stopped on construction done in violation of city ordinances or the State Building Code. library.municode.com: code of ordinances
- Where no specific penalty is set, a Morgantown code violation is punished by a fine of up to $500.00, and each day it continues is a separate offense. library.municode.com: code of ordinances
- Morgantown's building code penalty (Sec. 1701.99) reaches both the owner of a building where a violation exists and the builder or contractor who helped commit it, with a fine of up to $500.00 for each day, and lets the City Attorney sue to correct or abate the violation or prevent occupancy. library.municode.com: code of ordinances
- Morgantown requires a permit for every alteration, repair or construction except painting, wallpaper and minor repairs that do not affect structure or plumbing and cost $500.00 or less in labor and materials; the minor-repair exception does not apply in a FEMA flood plain. library.municode.com: code of ordinances
Applying for the permit in Berkeley County, Charleston and Morgantown
Berkeley County takes applications at its Martinsburg office, Charleston through its permit coordinator, and Morgantown only through its online portal.
- Berkeley County takes building permit applications at the Department of Building Permits and Inspections, 400 West Stephen Street, Suite 202, Martinsburg, 8 AM to 5 PM on weekdays; residential applications need detailed construction plans with footing, foundation, floor plan and cross sections. berkeleywv.org: Building Permit Process
- Charleston permit applications go to the Permit Coordinator, City of Charleston Building Department, 915 Quarrier St Suite 5; the permit number for online payment comes from the Permit Office at 304-348-6833. charlestonwv.gov: permits
- Morgantown accepts no paper permit applications: every building permit application goes through the Morgantown Access Portal, with a separate application for each scope of work. morgantownwv.gov: Permitting Licensing Registration
- Morgantown's deck, porch and ramp permit guidance asks contractors for the estimated job cost and property owners for the cost of materials, and recommends calling Development Services at 304-284-7401 before applying. morgantownwv.gov: Deck Porch Ramp Permit Guidance
Selling a West Virginia house with unpermitted work
We found no West Virginia statute that requires a seller to fill out a disclosure form for a house; the one hazard-specific duty in the code covers former drug labs. Unpermitted work surfaces instead through the certificate of occupancy where one is required, the permit record, and the agent's duty not to conceal.
- The one hazard-specific disclosure duty found in West Virginia statute: W. Va. Code 60A-11-3 directs the Department of Health to set rules requiring property owners, sellers and landlords to disclose a former clandestine drug lab to potential occupants of residential property. code.wvlegislature.gov: 60A 11 3
- The West Virginia Real Estate Commission may refuse, suspend or revoke the license of a real estate agent who commits or is a party to material fraud, misrepresentation or concealment that another person relies on. code.wvlegislature.gov document
- Berkeley County requires a Certificate of Occupancy before a building is used or occupied, issued only after final electrical, final grading and final building inspections, and it warns that this timing matters when scheduling real estate closings. berkeleywv.org: Certificate of Occupancy
- Charleston issues a Certificate of Occupancy only after all permits and required inspections are complete, fees are paid and subcontractors are registered. charlestonwv.gov: plans review
- Berkeley County's One Stop Permitting site lets the public search permit data online, and offers accounts for submitting and tracking applications. onestop.berkeleywv.org
- For permits issued before July 2020, Berkeley County keeps a separate Projects Database linked from its Building Permits and Inspections page. berkeleywv.org: Building Permits and Inspections
- Copies of Berkeley County building records can be requested under West Virginia's Freedom of Information law (Chapter 29B) on the county's request form, at $0.50 a page for letter or legal size, paid in advance. berkeleywv.org: 188
Before you list
Search the permit record for your address (Berkeley County's is online, with older permits in its projects database) and set it beside the work done while you owned the house. Legalize what is missing before closing is scheduled, because a certificate of occupancy waits on the final inspections.
If your contractor skipped the permit
West Virginia's Contractor Licensing Board publishes a standard contract that puts the permit on the contractor, and a willful violation of state or local building law is grounds for discipline. The board cannot award you money, so the contract is the lever.
- The board's standard construction contract form (Appendix A to 28 CSR 4) puts the permit on the contractor: the licensee is responsible for determining which permits are needed and for obtaining and paying for them. wvclboard.wv.gov: download resource.asp
- The Contractor Licensing Board's written-contract rule (28 CSR 4) recommends, but does not require, that a contract say who is responsible for obtaining and paying for any required permits. wvclboard.wv.gov: download resource.asp
- 28 CSR 4 took effect November 5, 2021. wvclboard.wv.gov: download resource.asp
- West Virginia's written-contract rule for licensed contractors (jobs of $10,000 or more) requires the contract to set out a description and cost of the work, signed by both sides, and requires the Contractor Licensing Board to publish a standard contract form. code.wvlegislature.gov document
- The same standard contract form has the contractor warrant that all work complies with building codes, that defective work will be corrected at no cost to the owner, and that the warranty lasts one year from completion. wvclboard.wv.gov: download resource.asp
- A licensed contractor who fails to execute the required written contract may be disciplined by the Contractor Licensing Board. wvclboard.wv.gov: download resource.asp
- Under W. Va. Code 30-42-15(g), causes for disciplining a contractor include willful or deliberate violation of state or local building laws, work below the local building code, and failing to satisfy a court or arbitration judgment; the board's sanctions include a fine of up to $1,000, but it has no power to award damages. code.wvlegislature.gov document
- The Contractor Licensing Board takes complaints against unlicensed contractors and licensed contractors working outside their classification on residential projects of $5,000 or more, but says it cannot help with building code violations, contract disputes, misused funds or workmanship, and needs a certified unsatisfied judgment or favorable arbitration ruling before disciplining a licensed contractor. wvclboard.wv.gov: index.asp
- Berkeley County's Notice to Homeowners warns that if a homeowner uses an unlicensed contractor, the county office will not help if the homeowner is unhappy with the work, and that not telling the office about contractors used will void the permit. berkeleywv.org: 585
What to send the contractor first
"The work you did at (your address) needed a building permit and none was pulled. If our contract follows the board's standard form, getting and paying for permits was your job. Please apply now and schedule the inspections, or tell me in writing why you will not." Keep the contract, receipts and messages.
Who can pull the permit
The West Virginia Contractor Licensing Act exempts work personally performed on a structure by its owner or occupant, and its definition of contractor excludes a person who personally does construction work on property they own or lease. When an owner applies for a building permit, state law requires the applicant either to show a contractor license or to file a written affidavit that they are not subject to licensure, so a homeowner signs that affidavit instead.
Owners may also do their own electrical work on property they or their immediate family own or lease (29-3B-3) and their own plumbing on a single-family home they or their immediate family own or lease (21-14-3). The statutes contain no resale or occupancy waiting period like Florida's; the local permit office still requires permits and inspections where the State Building Code is adopted.
Cited from W. Va. Code 30-42-6(c)(8); 30-42-3(d)(2); 30-42-10(a); 29-3B-3(a)(1); 21-14-3(c)(1): official text.
Common questions about unpermitted work in West Virginia
- What is the penalty for building without a permit in West Virginia?
- West Virginia has a State Building Code (legislative rule 87CSR4, adopted by the State Fire Commission under W. Va. Code 15A-11-5), but it only has force in the counties and cities that choose to adopt it, and the adopting local jurisdiction enforces it. Where it applies, W. Va. Code 15A-10-22(a) makes violating any rule promulgated by the State Fire Commission a misdemeanor punishable by a fine of up to $100, up to 90 days in county jail, or both, and each day illegal construction or alteration continues after the person knows or is officially notified that it is illegal counts as a separate offense. (W. Va. Code 15A-10-22(a); 15A-11-5(a), (d); 8-12-14; 8-11-1(a)(2), (c); 7-1-3n; 87CSR4)
- Can you get a permit after the work is done in West Virginia?
- No West Virginia statute creates an after-the-fact permit, but the State Building Code does provide for a work-before-permit fee. Rule 87CSR4 gives the adopted ICC codes the same force as if printed in the rule, and it adopts the 2018 IRC and IBC with amendments that leave their administrative Chapter 1 in place, so IRC R108.6 and IBC 109.4 (work commencing before permit issuance) are part of the State Building Code. Those sections subject anyone who starts permit-required work before getting the permit to an extra fee, on top of the regular permit fee; IRC R108.6 leaves the amount to the applicable governing authority and IBC 109.4 to the building official, so either way it is set locally. (87CSR4-4.1, 4.1.a, 4.1.h (adopting 2018 IRC R108.6 and 2018 IBC 109.4); W. Va. Code 15A-11-5(d); 8-11-1(c); 8-12-16)
- Who can pull a permit in West Virginia?
- The West Virginia Contractor Licensing Act exempts work personally performed on a structure by its owner or occupant, and its definition of contractor excludes a person who personally does construction work on property they own or lease. When an owner applies for a building permit, state law requires the applicant either to show a contractor license or to file a written affidavit that they are not subject to licensure, so a homeowner signs that affidavit instead. (W. Va. Code 30-42-6(c)(8); 30-42-3(d)(2); 30-42-10(a); 29-3B-3(a)(1); 21-14-3(c)(1))
Related situations in West Virginia
- A stop work order was posted: what it means and how to lift it
- How to find out if a permit was pulled, or report work with none
- A wall was removed without a permit
- Selling a house with unpermitted work
- Buying a house with unpermitted work
See which parts of the work needed a permit, then send us the details
Want help getting unpermitted work approved?
Tell us where your project stands. Where we have a vetted local pro who handles permits in West Virginia, we connect you; otherwise we reply with the exact steps and office links for your situation. Free to ask; no obligation.
PermitNotebook is not a government agency and does not file permits. This is a free referral request; we may earn a fee if you hire a pro we introduce. Partners never influence our permit data. Privacy policy.
Your local permit office
Enforcement, after-the-fact fees, and the exact fix-it process are local. We cover these West Virginia permit offices:
Official sources
This page summarizes state law from the official sources listed above, with a last checked date. It is not legal advice. Penalties and procedures are applied by local offices and courts case by case; for anything contested or high stakes, confirm with your permit office or a licensed professional in West Virginia.