New Hampshire

Building without a permit in New Hampshire

Quick answer

Since July 1, 2026, New Hampshire's building code penalties sit in the State Building Code chapter itself. A person who violates the building code, a local code adopted under it, or a permit condition is guilty of a misdemeanor (a felony for a business or other non-natural person) and faces a civil penalty of $275 for a first offense and $550 for later offenses, for each day the violation continues after conviction or after written notice from the town, whichever comes first.

Outline of New Hampshire beside its penalty for building without a permit: civil penalty a day $275 (first offense; $550 after that)
Who sets the penalty
State law
Fine in state law
A civil penalty of $275 a day for a first offense, $550 after that
Jail in state law
Not set in the building code; presumed class B, with no jail, unless class A penalties (up to a year) are sought or the case goes to superior court
Each day a new offense
Yes
Permit after the fact
Path in state law

What New Hampshire law says

Since July 1, 2026, New Hampshire's building code penalties sit in the State Building Code chapter itself. A person who violates the building code, a local code adopted under it, or a permit condition is guilty of a misdemeanor (a felony for a business or other non-natural person) and faces a civil penalty of $275 for a first offense and $550 for later offenses, for each day the violation continues after conviction or after written notice from the town, whichever comes first.

A misdemeanor whose class the law does not state is presumed to be class B, which carries no jail, unless the state seeks class A penalties, which allow up to a year in jail, or the case is brought in superior court (RSA 625:9, IV). Each day is a separate offense. The local building official may charge the offense as a lesser violation instead, and a town that wins in court recovers its costs and reasonable attorney fees.

The town's own building official enforces; where a town has no enforcement agency, the State Fire Marshal may enforce only on the town's written request.

Cited from RSA 155-A:4, I; RSA 155-A:7, I; RSA 155-A:8-a, I, II and V; RSA 625:9, IV: official text. Localities enforce these rules and may add their own fees and procedures on top.

Can you get a permit after the work is done?

No New Hampshire statute creates an after-the-fact or as-built permit; that process, and any added fee, is set by the town under its building code ordinance. What the statute does set is the correction path: the building official may issue a written cease and desist order that must state the corrective action required and a reasonable time to take it.

The owner has 20 days to file an answer; if the work is not corrected, the town may ask the district court to enforce the order, do the work itself, and place its costs as a lien on the property collected like real estate taxes. The building official also cannot issue a permit for work that would not comply with the code, so legalizing unpermitted work means bringing it up to code.

Cited from RSA 155-A:8-b, I, V, VIII and IX; RSA 155-A:4, V; RSA 155-A:8: official text.

The typical path, whatever your locality calls it: stop any ongoing work, contact the permit office before they contact you, apply for the permit describing what was actually built, and expect the office to require opening up or inspecting concealed work. Voluntarily coming forward generally goes better than waiting for a complaint or a sale to surface it.

What Manchester, Nashua and Concord add when the work came first

Manchester and Nashua add a surcharge equal to the permit fee, and Nashua caps it for homes. Concord raises the fee by a step that grows each time the same person or company does it. Worked below for a deck in Manchester, a garage in Nashua and a shed in Concord.

  • Manchester adds a surcharge equal to 100 percent of the permit fee to every permit for work started (or a use established) without a permit (Building Code §151.10.7). manchesternh.gov: BuildingCode
  • Manchester's building permit fee for decks, sheds, pools and additions is the estimated cost of the work multiplied by .01, and every building permit adds a $25.00 application fee. manchesternh.gov: Fees
  • Manchester's $.02 per square foot plan review fee does not apply to one- and two-family dwellings or accessory structures. manchesternh.gov: BuildingCode
  • The estimated cost must include all structural, electrical, plumbing and mechanical work, finishes, site work, overhead and profit; if it looks low, the building official may compute cost from floor area by type of construction or another industry-standard method. manchesternh.gov: BuildingCode
  • Nashua adds a surcharge of 100% of the applicable fee to a building permit issued after construction started without one, capped at $275 for residential work ($750 commercial). ecode360.com document
  • The same 100% surcharge, capped at $275, applies to residential electrical, plumbing and mechanical permits issued after work started. ecode360.com document
  • Nashua's permit fees are set in Revised Ordinances § 105-28, at rates amended 3-9-2021 by Ordinance O-21-045. ecode360.com document
  • Nashua building permits: a $50 nonrefundable application fee, then $0.18 per square foot of area for new one- and two-family buildings and additions, or $0.13 per square foot for residential alterations and repairs. ecode360.com document
  • Nashua rounds the total permit amount to the nearest dollar. ecode360.com document
  • Concord raises the building permit fee by 25% for a person's or company's first instance of starting work before the permit, 50% for a second, and 100% after that (Sec. 26-1-6(d)). library.municode.com: code of ordinances
  • The same 25%, 50% and 100% increases apply to Concord electrical permits for work started before the permit. concordnh.gov: Electrical 7120
  • Concord's building permit fee for construction or alteration is a $30.00 nonrefundable application fee plus $7.60 per $1,000 (or part of $1,000) of estimated cost. library.municode.com: code of ordinances
  • Concord's published fee schedules are dated as of July 1, 2020. concordnh.gov: building applications fees
  • Concord's 'estimated cost' is the Code Administrator-approved reasonable value of all labor, materials and equipment to finish the structure ready for occupancy, including electrical, mechanical and plumbing work, finishes, site work, overhead and profit. library.municode.com: code of ordinances
  • Concord's shed exemption covers only one-story sheds and playhouses up to 12 feet high and 60 square feet of floor area; larger sheds are not exempt under it. library.municode.com: code of ordinances

Manchester, a deck added to a house, $12,000 estimated cost, built without a permit

Building permit, $12,000 estimated cost x .01$120.00
Surcharge for work started without a permit, 100 percent of the permit fee$120.00
Application fee$25.00
Built first$265.00

One- and two-family work pays no plan review fee in Manchester. Any electrical permit for deck lighting is separate.

Nashua, a 24 by 24 foot detached garage (576 square feet) built without a permit

Building permit, 576 sq ft at $0.18$103.68
Surcharge, 100% of the fee, under the $275 residential cap$103.68
Building permit application fee$50.00
Building permit only, before rounding$257.36

Nashua rounds the total to the nearest dollar. The surcharge is applied here to the area fee, not the application fee. Nashua's planning and zoning review fee, which its fee example lists separately, and any electrical permit are not in this figure, so ask for both when you apply.

Concord, a 12 by 16 foot shed (192 square feet, so above the shed exemption) costing $6,000, the owner's first time

Nonrefundable application fee$30.00
Building permit, 6 thousands of estimated cost at $7.60$45.60
First occurrence of work before the permit: 25% of the fee$18.90
Built first$94.50

Concord's schedule counts the $30.00 application fee as part of the fee, so the 25% is applied to both lines; if the city leaves the application fee out, the total is a little lower. A second time is 50% and later ones 100%.

Before you call

Add up what the job cost, electrical, plumbing and mechanical included (Manchester and Concord price the permit on that figure), and measure its square footage (Nashua prices by area). Then ask: "Can I apply now for work already done at (your address), and which permits does it need?" In Concord, also ask whether it counts as a first occurrence.

Stop work orders and citations under New Hampshire's new law

Since July 1, 2026, a town's building official can serve a building code citation that the owner can answer by mail, but only after a written notice of the violation. Concord's ordinance still points to the older RSA 676 sections, but the state's building code enforcement procedure now sits in RSA 155-A; in Concord, work that continues after a stop work order is a separate offense.

  • Since July 1, 2026, a town's building official may serve a local building code citation that lets the owner plead guilty or no contest by mail; it may be served only after written notice of the violation, and one citation can charge at most 5 days of violation. gc.nh.gov: 155 A mrg
  • Manchester fines each building code violation, and every day it continues after a notice of violation is a separate offense; violations also go through the city's citation process. manchesternh.gov: BuildingCode
  • In Concord anyone may file a written complaint about a building code violation; the Code Administrator investigates and may order the violator to cease and desist or abate within a set time, then seek an injunction, a summons or a citation. library.municode.com: code of ordinances
  • Continuing work in Concord after a stop work order is a separate offense with its own penalties. library.municode.com: code of ordinances

Applying for the permit in Manchester, Nashua and Concord

Manchester posts its building application online and mails approved permits back, Nashua takes applications by email, and Concord works through its online portal.

  • Manchester's building permit application is available online (or mailed on request at 603-624-6450 or PCD@ManchesterNH.gov); electrical and plumbing applications must be printed, signed and mailed with the fees, and approved permits are mailed back. manchesternh.gov: Permit Applications
  • Manchester asks that certificate of occupancy requests for one- and two-family dwellings be made five business days ahead, and every inspection on every associated permit must be approved first. manchesternh.gov: Building
  • Nashua takes permit applications by email: fill in the PDF and send it to permits@nashuanh.gov, or apply at the Building Safety Department, 229 Main Street (2nd floor of City Hall), 603-589-3080. nashuanh.gov: Permits
  • Nashua's building and land use application requires the square footage of the construction or renovation and its approximate cost including plumbing, electrical, mechanical and fire suppression, and a plot plan for everything except interior renovations. nashuanh.gov document
  • Concord building permits are applied for in the Citizen Self Service (CSS) portal with all requested information and plans; the city then tells you the fee, which must be paid before the permit issues. concordnh.gov: building applications fees

Selling a New Hampshire house with unpermitted work

New Hampshire has no general seller disclosure form, and none of the disclosures it does require asks about permits. Unpermitted work surfaces through the buyer's inspection, the town's permit file, and the seller's agent, who must tell a buyer about a regulatory condition the agent actually knows of.

  • For a one- to 4-family home, the seller must disclose in writing, before or while the offer is prepared, information on the private water supply, the private sewage system, the insulation, any federally designated flood hazard zone and any residential heating oil underground storage tank, and the buyer signs a copy. None of the items concerns permits or unpermitted work. gc.nh.gov: 477 mrg
  • Before the purchase contract for any real property that includes a building, the seller must also disclose water supply and sewage disposal details (type, location, malfunctions, age, servicing), state in writing anything unknown, and have the buyer sign a copy. gc.nh.gov: 477 mrg
  • A seller's real estate agent must tell a prospective buyer, before the written offer, about any material physical, regulatory, mechanical or on-site environmental condition of the property the agent actually knows of, though the agent need not investigate. gc.nh.gov: 331 A mrg
  • Manchester links no online permit search; to see a property's permit file, submit the Access to Governmental Records form to the department holding the records (Planning and Community Development) or to the City Clerk. Viewing is free; copies are $1.00 for the first and $.50 for each additional. manchesternh.gov: Access to Governmental Records
  • Nashua links no online permit search; request permit records under RSA 91-A through the city's NextRequest portal (preferred), at the Records Administrator's office, or with the department. If a record is not readily available, the city responds within five business days; questions go to the Records Administrator at 603-589-3022. nashuanh.gov: Public Record Request
  • Concord's permit portal has a 'Search Public Records' tool for existing permits, plans, inspections and code cases. egselfservice.concordnh.gov: SelfService

Before you list

Get the permit file for your address (Concord's is searchable online; Manchester and Nashua answer a records request) and set it beside the work done while you owned the house. Legalize what is missing, and tell your agent, because the agent's duty to disclose starts once the agent knows.

If your contractor skipped the permit

New Hampshire licenses no general contractors, and its building statute puts the permit on the person responsible for the construction without saying whether that is the owner or the contractor (see who can pull the permit, below). So the tools are the contract, the construction defect notice the law requires before a lawsuit, and the consumer protection act.

  • A New Hampshire contract to build or improve a home for more than $5,000 must include a conspicuous notice of the contractor's right to try to resolve alleged construction defects before the homeowner sues (RSA 359-G:7). gc.nh.gov: 359 G mrg
  • Before suing a contractor over a construction defect, a homeowner must serve a written notice of claim at least 60 days ahead; the contractor has 30 days to offer money or repairs, propose an inspection, or reject the claim, and the notice pauses the limitations period for 60 days. gc.nh.gov: 359 G mrg
  • A person injured by an unfair or deceptive business practice can sue for actual damages or $1,000, whichever is greater, two to three times that for a willful or knowing violation, plus costs and reasonable attorney's fees. gc.nh.gov: 358 A mrg
  • Complaints about a contractor's unfair or deceptive practices go to the Attorney General's Consumer Protection and Antitrust Bureau in writing, on its consumer complaint form filed online or printed and mailed or emailed; an attorney reviews each complaint and may send it to the business for a response, but the Bureau cannot represent the consumer. doj.nh.gov: consumer complaints
  • The Consumer Protection Hotline is 1-888-468-4454 or (603) 271-3641, weekdays 8:00 am to 5:00 pm, email DOJ-CPB@doj.nh.gov. doj.nh.gov: consumer protection hotline

What to send the contractor first

"The work you built at (your address) went ahead without a building permit. Please apply for it and book the inspections within two weeks, or tell me in writing why not." If you later claim a defect, the written notice of claim has to be served at least 60 days before any lawsuit, by certified mail with return receipt requested or by hand, so keep the receipt and a copy.

Who can pull the permit

New Hampshire does not license general or residential contractors, so a homeowner may build without a contractor's license; the person responsible for the work must still get the building permit. State trade-licensing law expressly lets a homeowner do electrical work in a single family home they own and live in (or will live in), and lets a property owner do plumbing in their own single-family detached or townhouse residence, including new construction, provided the plumbing meets the state plumbing code.

A homeowner may also do fuel gas fitting in an existing single family home that is their primary residence, subject to code, application and inspection requirements. No statute imposes a sale or occupancy restriction on owner-built homes.

Cited from RSA 155-A:4, I; RSA 319-C:15, II; RSA 153:36, I and VIII(c): official text.

Common questions about unpermitted work in New Hampshire

What is the penalty for building without a permit in New Hampshire?
Since July 1, 2026, New Hampshire's building code penalties sit in the State Building Code chapter itself. A person who violates the building code, a local code adopted under it, or a permit condition is guilty of a misdemeanor (a felony for a business or other non-natural person) and faces a civil penalty of $275 for a first offense and $550 for later offenses, for each day the violation continues after conviction or after written notice from the town, whichever comes first. (RSA 155-A:4, I; RSA 155-A:7, I; RSA 155-A:8-a, I, II and V; RSA 625:9, IV)
Can you get a permit after the work is done in New Hampshire?
No New Hampshire statute creates an after-the-fact or as-built permit; that process, and any added fee, is set by the town under its building code ordinance. What the statute does set is the correction path: the building official may issue a written cease and desist order that must state the corrective action required and a reasonable time to take it. (RSA 155-A:8-b, I, V, VIII and IX; RSA 155-A:4, V; RSA 155-A:8)
Who can pull a permit in New Hampshire?
New Hampshire does not license general or residential contractors, so a homeowner may build without a contractor's license; the person responsible for the work must still get the building permit. State trade-licensing law expressly lets a homeowner do electrical work in a single family home they own and live in (or will live in), and lets a property owner do plumbing in their own single-family detached or townhouse residence, including new construction, provided the plumbing meets the state plumbing code. (RSA 155-A:4, I; RSA 319-C:15, II; RSA 153:36, I and VIII(c))

Related situations in New Hampshire

See which parts of the work needed a permit, then send us the details

Want help getting unpermitted work approved?

Tell us where your project stands. Where we have a vetted local pro who handles permits in New Hampshire, we connect you; otherwise we reply with the exact steps and office links for your situation. Free to ask; no obligation.

PermitNotebook is not a government agency and does not file permits. This is a free referral request; we may earn a fee if you hire a pro we introduce. Partners never influence our permit data. Privacy policy.

Your local permit office

Enforcement, after-the-fact fees, and the exact fix-it process are local. We cover these New Hampshire permit offices:

Official sources

This page summarizes state law from the official sources listed above, with a last checked date. It is not legal advice. Penalties and procedures are applied by local offices and courts case by case; for anything contested or high stakes, confirm with your permit office or a licensed professional in New Hampshire.