Building without a permit in Montana
Quick answer
Montana makes a knowing violation of the state building, plumbing, elevator, or electrical code, or of a county, city, or town building code, a misdemeanor for any owner, builder, contractor, or other person taking part in the construction; so is failing to comply with a correction order within 30 days of service or within the time the building department sets, whichever is longer (MCA 50-60-110). The statute sets no fine, so the general misdemeanor default applies: up to 6 months in the county jail, a fine of up to $500, or both (MCA 46-18-212).
- Who sets the penalty
- State law
- Fine in state law
- Up to $500 (misdemeanor)
- Jail in state law
- Yes, up to 6 months
- Each day a new offense
- Not stated
- Permit after the fact
- Path in state law
Does a building department cover your Montana address?
For a one- to four-unit home, Montana's building code is enforced only inside a certified city, county or town program; outside one, no building department enforces it on a house, though the state's electrical and plumbing permits still apply to work by electricians and plumbers. So check the state's list before anything else.
- A Montana city, county or town may enforce a building code only once the state Building Codes Program has certified its enforcement program. bsd.dli.mt.gov: certified government
- The state's list of certified programs includes Billings, Bozeman, the City of Missoula and Missoula County, and marks some programs, such as Pondera County's, as commercial only; all other areas are under the State Building Codes Bureau. bsd.dli.mt.gov: certified government
Check the list first
Find your city or county on the state's list of certified programs and check its codes column: a program marked commercial only does not cover a house. If yours covers houses, call that building department about the work; if not, the questions that remain are the state electrical and plumbing permits, which the Department of Labor and Industry issues.
What Montana law says
Montana makes a knowing violation of the state building, plumbing, elevator, or electrical code, or of a county, city, or town building code, a misdemeanor for any owner, builder, contractor, or other person taking part in the construction; so is failing to comply with a correction order within 30 days of service or within the time the building department sets, whichever is longer (MCA 50-60-110).
The statute sets no fine, so the general misdemeanor default applies: up to 6 months in the county jail, a fine of up to $500, or both (MCA 46-18-212). For houses the reach is narrower than it looks: the state building code does not apply to residential buildings of fewer than five units, their attached structures, or owner-use private garages and storage buildings unless the local government opts in, and the state may not enforce it on them (MCA 50-60-102(1)(a), (2)).
So on a one- to four-unit home outside a certified city, town, or county program, no building department enforces the general building code; the one exception is the code's energy conservation provisions, which do apply to homes and are enforced through the builder self-certification program (MCA 50-60-102(5)). Inside a certified program the local building department enforces its code, and courts may enjoin violations (MCA 50-60-106, 50-60-109).
The Department of Labor and Industry still enforces state electrical and plumbing permits outside certified programs: energizing an electrical installation with no electrical permit is a misdemeanor (MCA 50-60-607), and violating the state plumbing permit law is a misdemeanor fined $10 to $100 per offense (MCA 50-60-515).
Cited from MCA 50-60-110; 46-18-212; 50-60-102(1)(a), (2), (5); 50-60-106; 50-60-109; 50-60-607; 50-60-515: official text. Localities enforce these rules and may add their own fees and procedures on top.
Can you get a permit after the work is done?
No Montana statute creates a general as-built or after-the-fact building permit. The state Building Codes Program says a building permit is required before construction starts and that buildings started without one may be assessed an investigation fee and may need significant corrective construction, but that applies only to buildings that need a state building permit: one- to four-unit homes, their attached structures, and owner-use garages and storage buildings outside a certified local program are exempt from the state building code (MCA 50-60-102(1)(a), (2)).
Where a state plumbing permit is required, anyone who starts the work without one must pay double the permit fee if later allowed to obtain the permit, unless the work was a proven emergency (MCA 50-60-509), and the department may order plumbing work stopped after a hearing (MCA 50-60-512). Inside a certified city, town, or county program, the building department may order in writing the remedying of any code violation found during construction, with time to comply, and may refuse to let construction begin until a permit issues (MCA 50-60-106(2)(d), (3)(b)); any local fee multiplier or legalization step is set by that jurisdiction.
Cited from MCA 50-60-102(1)(a), (2); 50-60-509; 50-60-512; 50-60-106(2)(d), (3)(b); Montana DLI Building Codes Program, 'Is a State Building Permit Needed?': official text.
The typical path, whatever your locality calls it: stop any ongoing work, contact the permit office before they contact you, apply for the permit describing what was actually built, and expect the office to require opening up or inspecting concealed work. Voluntarily coming forward generally goes better than waiting for a complaint or a sale to surface it.
What the City of Missoula and Bozeman add when the work came first
The City of Missoula doubles the permit fee and also bills the staff time spent investigating. Bozeman's code allows an extra fee of up to twice the permit fee, but its schedule does not set the amount. Billings fines violations as municipal infractions. Worked below for the same finished basement in both cities.
- The City of Missoula's current building fee schedules were adopted by Resolution 8970 on August 17, 2026 and took effect October 1, 2026. ci.missoula.mt.us: Resolution 8970
- Missoula charges double the permit fee when work starts without a permit, or the Stop Work Order fee if that is more; emergency repairs may start first if a permit is applied for on the next working business day. ci.missoula.mt.us: Resolution 8970
- On top of the permit fee, Missoula collects an investigation fee at actual staff time (one-hour minimum) whenever work was started without a permit, whether or not a permit is then issued. ci.missoula.mt.us: Resolution 8970
- Missoula's building permit fee for work valued at $29,001 to $30,000 is $830. ci.missoula.mt.us: Resolution 8970
- Missoula's residential (one- and two-unit) plan review fee is 30% of the building permit fee, rounded up to the nearest dollar. ci.missoula.mt.us: Resolution 8970
- Missoula adds a 5% technology fee to the total cost of each permit. ci.missoula.mt.us: Permit Fee Schedule Building Electrical Mechanical...
- For remodels that add no square footage, such as finishing a basement, Missoula prices the permit on an estimated valuation of the work. ci.missoula.mt.us: Building Permit Valuation Plan Review Packet
- Bozeman's code adds a fee, set by the Building Division, for work started before permits are obtained, on top of the required fees and capped at twice the permit fee. library.municode.com: code of ordinances
- Bozeman's FY 2027 Building Division fee schedule took effect August 1, 2026. bozemanmt.gov document
- Bozeman prices remodels and other work on existing square footage with its generic valuation table (Table C), based on the total value of materials and labor. bozemanmt.gov document
- For work valued from $25,001 to $50,000, Bozeman charges $391.75 for the first $25,000 plus $10.10 for each additional $1,000 or fraction of it. bozemanmt.gov document
- Bozeman's building plan review fee is 65% of the permit fee for residential (IRC) as well as commercial projects. bozemanmt.gov document
- In Billings, violating the adopted building codes is a municipal infraction punished by civil penalties, and each day the violation continues is a separate offense. library.municode.com: code of ordinances
City of Missoula, a basement finished without a permit, valued at $29,001 to $30,000
| Building permit | $830.00 |
| Residential plan review, 30% of the permit fee | $249.00 |
| Double fee because work began without a permit | $830.00 |
| Before the technology and investigation fees | $1,909.00 |
Add Missoula's 5% technology fee on the permit's total and the investigation fee, which is billed at staff time with a one-hour minimum. Land use and engineering review fees are paid at intake, and trade permits are separate.
Bozeman, the same basement, valued at $30,000
| Building permit, first $25,000 | $391.75 |
| Building permit, 5 more $1,000s at $10.10 | $50.50 |
| Plan review, 65% of the permit fee | $287.46 |
| Before the fee for starting first | $729.71 |
The extra fee for work begun before the permit is set by the Building Division and can be as much as twice the permit fee; ask for the figure. Electrical, plumbing and mechanical permits are separate and priced the same way.
Bozeman, the same basement if the extra fee is set at its cap, twice the permit fee
| Building permit, first $25,000 | $391.75 |
| Building permit, 5 more $1,000s at $10.10 | $50.50 |
| Plan review, 65% of the permit fee | $287.46 |
| Extra fee at its cap: the first $25,000 line twice | $783.50 |
| Extra fee at its cap: 5 more $1,000s at $10.10, twice | $101.00 |
| The most it can be, before trade permits | $1,614.21 |
Before you call
Collect the receipts for materials and labor, since both cities value the work on them, and take photos. Then ask the building division: "Work was finished at (your address) before a permit was issued. What will the added fee for that be, and which code edition will you review it under?"
Penalties, stop work orders and the 2027 code change
Billings and Bozeman count each day of a violation as a separate offense, and the City of Missoula charges for a stop work order. Billings and Bozeman also move to the 2024 codes on January 1, 2027, so an application made after that date is reviewed under the newer code.
- A stop work order in the City of Missoula carries a $250 fee. ci.missoula.mt.us: Permit Fee Schedule Building Electrical Mechanical...
- Violating Bozeman's building chapter, a building permit or an adopted code is a misdemeanor fined up to $500.00 plus costs, and each day is a separate offense. library.municode.com: code of ordinances
- In Billings, a first municipal infraction carries a civil penalty of up to $300.00, and each repeat violation within 12 months up to $500.00, with every day of violation a separate infraction. library.municode.com: code of ordinances
- In Billings, besides the civil penalty, the municipal court can order the owner to stop or fix the violation, let the city fix it, and enter the city's costs as a judgment or assess them against the property. library.municode.com: code of ordinances
- In Missoula, a violation of the adopted building codes is a municipal ordinance violation, penalized within the limits state law allows. ci.missoula.mt.us: Municipal Code Title 15 Buildings Construction
- Montana has adopted the 2024 building codes, and they take effect in Billings on January 1, 2027. billingsmt.gov: Building
- Bozeman applications submitted on or after January 1, 2027 must be designed to the 2024 ICC codes as amended by state rule. bozemanmt.gov: building
- Billings takes building permit applications only through its CityView online portal. billingsmt.gov: Faq
- Missoula's permit coordinators answer at (406) 552-6060 or coordinators@ci.missoula.mt.us, and building code questions go to (406) 552-6630 or BLDG@ci.missoula.mt.us. ci.missoula.mt.us: Building Division
- Bozeman's Building Division answers at (406) 582-2375 ext. 1 or building@bozemanmt.gov, with a front counter at 20 East Olive St. bozemanmt.gov: building
Selling a Montana house with unpermitted work
Montana's disclosure law asks the question directly: the seller must say, if they know, whether substantial additions or alterations were made without a building permit. Unless the contract or the offer waives it, the buyer then has 3 days to walk away.
- In any transfer of a Montana home, the seller must give the buyer a disclosure statement of adverse material facts the seller actually knows, before or when the contract is signed. mca.legmt.gov document
- The statement must disclose, if the seller knows, whether any substantial additions or alterations were made without a building permit, along with known problems with structural systems, roof, foundation, plumbing, electrical and heating. mca.legmt.gov document
- The law covers homes of one to four units, individually owned units in any building, condominiums, and manufactured homes made part of the real property. mca.legmt.gov document
- Unless the parties agree otherwise in writing, a contract is not effective until 3 days after the buyer receives the statement, and the buyer may withdraw without penalty during that time; the statement is not a warranty. mca.legmt.gov document
- If the statement arrives after the contract is signed, the buyer has 3 days from delivery to rescind by a separately signed written statement, unless the buyer waived that right in the offer. mca.legmt.gov document
- No statement is required for court-ordered transfers, divorce transfers between spouses, foreclosure-related transfers, transfers between co-owners or to a spouse, child or parent, or when the buyer waived it in the contract. mca.legmt.gov document
- The statement is the seller's alone, not the agent's, and a seller may not be responsible for errors based on information from a reliable third party such as a local government agency. mca.legmt.gov document
- A seller's real estate agent must tell the buyer about adverse material facts the agent knows, but need not inspect the property or verify the seller's statements. mca.legmt.gov document
- The City of Missoula's Permit Atlas map and its Permit & Licensing Portal show current and past permits by address without a login, back to 1991; older records and approved plans need a records request. ci.missoula.mt.us: Research a Property
- Bozeman's online permit lookup, linked as 'Look Up Permit' from the Building page, searches by application number, address, parcel number or name. bozn-egov.aspgov.com: selectpermit
- Anyone can search Billings permits in CityView's Permit Search by application number, address, tax parcel ID or a contact's name or address. cityview.billingsmt.gov: Locator
Before you list
Search the permit record for your address (all three cities' are online) and set it beside every substantial addition or alteration you know of, including work done before you bought the house, because the statement asks about any you actually know were done without a permit. Legalizing it first changes the answer.
If your contractor skipped the permit
No Montana statute says who pulls a building permit, so the state's consumer office tells homeowners to put it in the contract. The state plumbing permit is different: a plumber in the business must get it before starting, and plumbing started without one costs double the permit fee (see the after-the-fact section above). When it goes wrong, the licensing program cannot get your money back; a bond or a court may be the way to recover.
- Anyone in the business of installing, altering or repairing plumbing must get a permit from the Department of Labor and Industry before starting the work. mca.legmt.gov document
- Montana's Office of Consumer Protection advises getting a written contract that states whether the contractor will obtain the necessary licenses and permits, and checking with the local building inspector on which permits the job needs. dojmt.gov: choosing a contractor
- Billings tells owners that obtaining permits is the owner's responsibility unless delegated to the contractor, in which case the owner should confirm the contractor got every permit and passed every inspection. billingsmt.gov: Faq
- Montana's contractor license law treats fraud, misrepresentation, deception or concealment of a material fact in a contract or in written communications with a client as unprofessional conduct. mca.legmt.gov document
- Complaints about contractor registration or licensing go to the Department of Labor and Industry's Employment Standards Division through its Citizen Portal. erd.dli.mt.gov: complaints
- A Department of Labor and Industry licensing board or program cannot award damages, order a refund or settle a private dispute; its complaint process is licensing enforcement only. bsd.dli.mt.gov: filing complaint
- The Office of Consumer Protection warns that the state licensing board does not investigate poor workmanship or an unfinished job or pay compensation; a bond may be the only way to recover. dojmt.gov: choosing a contractor
- To complain to the Office of Consumer Protection, contact the business first, then use the office's complaint form; questions go to 406-444-4500 or contactocp@mt.gov. dojmt.gov: consumer complaints
What to send the contractor first
"Our contract covers the work at (your address), and no building permit was pulled for it. Please get the permit issued and the inspections booked, or tell me in writing why not, and send me your bonding company's name." Keep the contract, receipts and messages.
Who can pull the permit
Montana's construction contractor license law does not apply to an owner working on the owner's own property, occupied or not, unless the owner builds to promptly sell, and even then the exemption holds if the owner has lived there as a primary residence for at least the last 12 months (MCA 37-45-104(13)). An individual needs no electrician's license to do electrical work on the individual's own property or residence kept for the individual's own use, except work on a grid-tied generator (MCA 37-68-103(3)); the state issues a homeowner electrical permit for this, with state inspections.
An owner of a single-family residence used only for the owner's personal use may install all sanitary plumbing and potable water piping without a plumbing license (MCA 37-69-102(1)(a)) and, where the state has jurisdiction, without a state plumbing permit (MCA 50-60-506(4)). Certified local jurisdictions may still require their own building permits.
Cited from MCA 37-45-104(13); 37-68-103(3); 37-69-102(1)(a); 50-60-506(4): official text.
Common questions about unpermitted work in Montana
- What is the penalty for building without a permit in Montana?
- Montana makes a knowing violation of the state building, plumbing, elevator, or electrical code, or of a county, city, or town building code, a misdemeanor for any owner, builder, contractor, or other person taking part in the construction; so is failing to comply with a correction order within 30 days of service or within the time the building department sets, whichever is longer (MCA 50-60-110). The statute sets no fine, so the general misdemeanor default applies: up to 6 months in the county jail, a fine of up to $500, or both (MCA 46-18-212). (MCA 50-60-110; 46-18-212; 50-60-102(1)(a), (2), (5); 50-60-106; 50-60-109; 50-60-607; 50-60-515)
- Can you get a permit after the work is done in Montana?
- No Montana statute creates a general as-built or after-the-fact building permit. The state Building Codes Program says a building permit is required before construction starts and that buildings started without one may be assessed an investigation fee and may need significant corrective construction, but that applies only to buildings that need a state building permit: one- to four-unit homes, their attached structures, and owner-use garages and storage buildings outside a certified local program are exempt from the state building code (MCA 50-60-102(1)(a), (2)). (MCA 50-60-102(1)(a), (2); 50-60-509; 50-60-512; 50-60-106(2)(d), (3)(b); Montana DLI Building Codes Program, 'Is a State Building Permit Needed?')
- Who can pull a permit in Montana?
- Montana's construction contractor license law does not apply to an owner working on the owner's own property, occupied or not, unless the owner builds to promptly sell, and even then the exemption holds if the owner has lived there as a primary residence for at least the last 12 months (MCA 37-45-104(13)). An individual needs no electrician's license to do electrical work on the individual's own property or residence kept for the individual's own use, except work on a grid-tied generator (MCA 37-68-103(3)); the state issues a homeowner electrical permit for this, with state inspections. (MCA 37-45-104(13); 37-68-103(3); 37-69-102(1)(a); 50-60-506(4))
Related situations in Montana
- A stop work order was posted: what it means and how to lift it
- How to find out if a permit was pulled, or report work with none
- A wall was removed without a permit
- Selling a house with unpermitted work
- Buying a house with unpermitted work
See which parts of the work needed a permit, then send us the details
Want help getting unpermitted work approved?
Tell us where your project stands. Where we have a vetted local pro who handles permits in Montana, we connect you; otherwise we reply with the exact steps and office links for your situation. Free to ask; no obligation.
PermitNotebook is not a government agency and does not file permits. This is a free referral request; we may earn a fee if you hire a pro we introduce. Partners never influence our permit data. Privacy policy.
Your local permit office
Enforcement, after-the-fact fees, and the exact fix-it process are local. We cover these Montana permit offices:
Official sources
This page summarizes state law from the official sources listed above, with a last checked date. It is not legal advice. Penalties and procedures are applied by local offices and courts case by case; for anything contested or high stakes, confirm with your permit office or a licensed professional in Montana.